Key Facts

Permit trigger
Any new, enlarged, altered or repaired 1-2 family dwelling
Issuing office
City building inspector
Application form
State uniform dwelling permit application
New dwelling permit validity
2 years from issuance (Sec. 54-10(c))
Other permit validity
1 year from issuance
Permit voided if unstarted
12 months after issuance
Final inspection window
Requested within 30 days of completion

Summary

De Pere requires a building permit before any one- or two-family dwelling is built, enlarged, altered or repaired, plus for accessory structures like garages, sheds, gazebos and fences. City Code Sec. 54-3(e) puts issuance with the building inspector on the state uniform dwelling permit application form, and permits lapse if work is not started or is abandoned for 12 months.

Building permits required. No one-family or two-family dwelling shall be built, enlarged, altered or repaired unless a building permit for that work shall first be obtained by the owner or his or her agent from the building inspector. Application for a building permit shall be in writing upon the form designated by the state uniform dwelling permit application.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 9).

Full Breakdown

Sec. 54-3(e) of the Code of Ordinances bars construction, enlargement, alteration or repair of a one- or two-family dwelling without a permit obtained by the owner or an agent from the building inspector, filed on the state uniform dwelling permit application form. Sec. 54-3(f)(2) extends the same permit requirement to accessory buildings and structures, including detached garages, sheds, roof-covered patios, gazebos, pergolas and fences. Applicants for new construction or remodeling must submit two sets of plans, one paper and one digital, along with a site plan and soil erosion control plan; alteration and remodeling projects need complete building, electrical, plumbing and HVAC plans under Sec.

54-3(f)(4). Once issued, a permit is posted at the site and kept on file with the building inspection division; under Sec. 54-3(f)(5) it becomes null and void if work is not commenced within 12 months, or if construction is suspended or abandoned for 12 months at any point after starting. Sec. 54-10(c) sets overall permit duration: two years from issuance for permits covering initial construction of one- and two-family dwellings, and one year for all other permits, with renewal of an expired permit carrying its own fee.

Before concealment, Sec. 54-3(f)(7) requires inspections at defined stages, erosion control, sanitary/storm/water service, footing and foundation, underground drains, rough construction, and insulation, each triggered by the applicant's notice to the building inspector. A final inspection is required before occupancy: the applicant must request it within 30 days of completing the work, and the inspector must perform it within five business days.

Violations & Fines

No permit-specific fine attaches to Sec. 54-3 itself, so the general Code penalty in Sec. 1-11(a) applies: a forfeiture of not less than $1.00 nor more than $2,000.00 for each offense, rising to $10.00-$2,000.00 for a second offense under Sec. 1-11(b). Sec. 54-3(f)(7)g also treats a missed final inspection, uncorrected violations, or unpaid prior permit fees as a violation subject to citation and a reinspection fee, and the inspector may refuse further permits to a noncompliant applicant. An uncorrected violation can draw a stop-work order under Sec. 54-3(f)(7)h.

Frequently Asked Questions

Do I need a permit to build a shed or fence in De Pere?
Yes. Sec. 54-3(f)(2) requires a building permit for any accessory building or structure, including detached garages, sheds, roof-covered patios, gazebos, pergolas and fences, before it is constructed, enlarged, altered or repaired.
How long does a De Pere building permit stay valid?
Sec. 54-10(c) sets two years for permits covering new construction of a one- or two-family dwelling and one year for every other permit. Sec. 54-3(f)(5) separately voids any permit if work has not started within 12 months or sits suspended for 12 months.
What happens if I skip the final inspection?
Sec. 54-3(f)(7)g makes failing to obtain a final inspection, correct noted violations, or pay prior permit fees a violation subject to citation and a reinspection fee, and the building inspector may refuse to issue future permits to that applicant.
What plans must I file with a De Pere building permit application?
Sec. 54-3(f)(4) requires two sets of plans, one paper and one digital, a comprehensive site plan and a soil erosion control plan for new construction, plus complete building, electrical, plumbing and HVAC plans for any alteration or remodeling project.

Sources & Official References

Other rules in De Pere

All De Pere rules

Compare De Pere to another location·View the Wisconsin building safety overview

Get notified when Building Permits in De Pere, WI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in Brown County handle building permits.

Green Bay, WI
Some Restrictions
Ashwaubenon, WI
Some Restrictions