Issuing official
Construction Official, after final development approval
Lot requirement
Lot must abut a street giving access to the building
Waste form deadline
Faxed to Middlesex County within 48 hours of issuance
Conditional permit term
Three months, not renewed
Zoning permit fee
$50, valid for one year
New construction fee
$0.05 per cubic foot, $200 minimum

Summary

In East Brunswick Township, the Construction Official issues no building permit until final approval has been granted to the application for development. A building or structure also needs a lot abutting a street, and the permittee must send a construction and demolition waste form to Middlesex County within 48 hours.

§ 132-56. Building Permits. ... A. Building Permits. ... No building permit shall be issued by the Construction Official until final approval has been granted to the application for development. B. At the time of issuance of any building permit, the building code official will provide written instruction on proper disposal and recycling of construction and demolition waste and furnish a Notification of Construction/Demolition Activity Form. The Form must be filled out by the permittee and faxed to the Middlesex County Division of Solid Waste Management (MCDSWM) within 48 hours of the issuance of a municipal permit. ... C. Building Lots to Abut Street. No permit for the erection of a building or structure shall be issued unless the lot abuts a street giving access to such proposed building or structure.

Full Breakdown

Section 132-56 governs when a building permit can be issued in East Brunswick Township. Under subsection A, the Construction Official issues no building permit until final approval has been granted to the application for development. Subsection D adds that the Chief Construction Official issues no building permit for any home in a subdivision until final subdivision approval has been granted by the Planning Board. Subsection C requires that the lot abut a street giving access to the building or structure: an existing state, county or municipal street, a street on a plat approved by the appropriate Board, or a street on a plat filed with the county recording officer before the governing ordinance. The street must be certified as suitably improved to the satisfaction of the Township Council, or the improvement must be assured by a performance guarantee.

At issuance, the building code official gives the permittee written instruction on disposal and recycling of construction and demolition waste and a Notification of Construction/Demolition Activity Form. The permittee fills it out and faxes it to the Middlesex County Division of Solid Waste Management within 48 hours (subsection B).

Conditional building permits are available under § 132-56(E) and § 132-57 after site plan or subdivision approval but before corrected plans are filed. A conditional permit is valid for three months from issuance and is not renewed; construction then ceases until a full building permit is obtained.

A zoning permit is a separate, earlier step. Section 132-56.1 requires one from the Zoning Officer before construction starts on fences six feet or less in height, private pools, new single-family dwellings, additions to a single-family dwelling over 150 square feet, signage unless exempt, shed installations, and new impervious surfaces greater than 50 square feet. The zoning permit fee is $50 and the permit is valid for one year.

Construction permit fees under § 75-3 are paid before the permit is issued. The building subcode fee is $0.05 per cubic foot for new construction with a $200 minimum, and $30 per $1,000 of estimated cost for renovations, alterations and repairs with a $75 minimum.

Violations & Fines

Under § 132-58, no land or new construction can be occupied until the Construction Official issues a certificate of occupancy. Transferring or occupying a home without one, where required improvements are not installed, is a violation by the subdivider or seller and the purchaser or occupant, punishable by a fine not to exceed five hundred dollars ($500.) or imprisonment for not more than ninety (90) days, or both.

Frequently Asked Questions

When will East Brunswick Township issue a building permit?
Not until final approval has been granted to the application for development, under Township Code § 132-56(A). For a home in a subdivision, the Chief Construction Official also waits for final subdivision approval from the Planning Board, and the lot must abut a street giving access to the building.
Do I need a zoning permit as well in East Brunswick Township?
Often the answer is yes, because § 132-56.1 requires a zoning permit before construction for fences six feet or less, private pools, new single-family dwellings, additions over 150 square feet, shed installations, signage unless exempt, and new impervious surface greater than 50 square feet. The application fee is $50.
What is the waste form handed out with a building permit?
Section 132-56(B) requires the building code official to provide written instruction on disposal and recycling of construction and demolition waste, plus a Notification of Construction/Demolition Activity Form. The permittee must fill it out and send it to the Middlesex County Division of Solid Waste Management within 48 hours.
Can I start work before my corrected site plans are filed?
Possibly, through a conditional building permit under §§ 132-56(E) and 132-57 after site plan approval. It is valid for three months and is not renewed, and the applicant proceeds at his own risk without assurance that a permit for the entire structure will be granted.

Sources & Official References

Other rules in East Brunswick

All East Brunswick rules

Compare East Brunswick to another location·View the New Jersey building safety overview

Get notified when Building Permits in East Brunswick, NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in this county handle building permits.

Edison, NJ
Some Restrictions