Permit required before
Construction, alteration or repair of any structure
Fees set by
Chapter 20 fee schedule
Application must include
Plat/sketch plus plans and specifications
Enforcement tool
Written stop-work order, Sec. 105-81
Occupancy
Certificate of occupancy required, Sec. 105-82
Appeal path
Board of zoning appeals, then state commission

Summary

In the City of Gary, a building permit from the building commissioner is required before starting construction, alteration or repair of any building or structure, and all permit fees set by Chapter 20 must be paid to the building department before work begins, under Section 105-108 of the city code.

A permit shall be obtained before beginning construction, alteration or repair of any building or structure using forms furnished by the building commissioner, and all fees required by chapter 20 shall be paid to the building department of the city.

Full Breakdown

Section 105-108 of the Gary Municipal Code requires a permit before any construction, alteration or repair of a building or structure begins, using forms the building commissioner supplies, with all fees set by Chapter 20's fee schedule paid to the city's building department. Section 105-109 spells out what the application must include: a plat or sketch showing lot boundaries, plans and specifications describing the work, and, where the project is covered by a state design release under IC 22-15-3-1, a copy of that release for the building commissioner before a permit issues.

Section 105-112 requires the building commissioner to review every application not just for code compliance but for flood safety in floodplain areas with special flood hazards, checking that new construction and substantial improvements are reasonably safe from flooding, anchored against flotation and collapse, and built with flood-resistant materials and methods. Section 105-80 gives the building commissioner authority to administer and enforce the article, but bars arbitrary or discriminatory enforcement or discretion beyond what the ordinance itself prescribes. If work proceeds contrary to the code, Section 105-81 lets the commissioner issue a written stop-work order to anyone doing or causing the work, who must halt until the commissioner authorizes resuming.

Section 105-82 backs the permit requirement with an occupancy check: no certificate of occupancy may issue for a building built after the ordinance's adoption unless it was constructed under the article's provisions, and it is unlawful to occupy such a building without a full, partial or temporary certificate of occupancy from the commissioner. Appeals from the commissioner's decisions go first to the board of zoning appeals and then to the state fire prevention and building safety commission under Section 105-51.

Violations & Fines

Building, altering or repairing a structure without the Section 105-108 permit, or occupying a new building without the certificate of occupancy Section 105-82 requires, is unlawful under the Gary code. The building commissioner can halt noncompliant work immediately with a written stop order under Section 105-81, and decisions denying or revoking permits may be appealed first to the board of zoning appeals and then to the state fire prevention and building safety commission per Section 105-51.

Frequently Asked Questions

Do I need a permit to remodel a house in Gary?
Yes. Section 105-108 requires a building permit, issued on forms from the building commissioner, before beginning construction, alteration or repair of any building or structure, and the fees set in Chapter 20 must be paid to the city's building department first.
What has to be submitted with a Gary building permit application?
Section 105-109 requires a plat or sketch showing the lot's boundaries and proposed location, plus plans and specifications describing the work. Projects covered by a state design release under IC 22-15-3-1 must also submit a copy of that release before the permit can be issued.
Can I occupy a new building in Gary before final approval?
No. Section 105-82 makes it unlawful to occupy a building constructed after the ordinance's adoption unless a full, partial or temporary certificate of occupancy has been issued by the building commissioner confirming the work complied with the article.

Sources & Official References

Other rules in Gary

All Gary rules

Compare Gary to another location·View the Indiana building safety overview

Get notified when Building Permits in Gary, IN changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.