Key Facts
- Building code adopted
- Florida Building Code, latest edition (§ 7-16)
- Fire plan review
- Required before any construction, alteration or demolition permit issues (§ 10-3.17)
- Fire code edition
- FFPC 8th Edition, effective June 1, 2024 (§ 10-3.03)
- Fees before inspection
- All permit fees paid first (§ 7-19)
- Refund window
- Written request within six months; 50 percent of permit fee (§ 7-20(b))
- Fee schedule
- Set by city council resolution (§ 7-20(c))
Summary
Jacksonville Beach adopts the latest edition of the Florida Building Code for the construction, maintenance, and repair of buildings, including permits and penalties, so that code supplies the permit rules. On top of that, no permit for construction, erection, alteration, repair, or demolition issues until the fire official has reviewed the plans and found them compliant with the fire chapter and the adopted Florida Fire Prevention Code.
There is hereby adopted by the city for the purpose of establishing rules and regulations for the construction, maintenance, and repair of buildings, including permits and penalties, that certain code known as the Florida Building Code, latest edition. ... A permit for construction, erection, alteration, repair, or demolition shall not be issued until the fire official has reviewed the plans and specifications for such proposal and the fire official has found the plans to be in compliance with this chapter and adopted edition of the FFPC.
Official source re-checked November 3, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 60).
Full Breakdown
Section 7-16 of the Jacksonville Beach Code adopts the Florida Building Code, latest edition, for the purpose of establishing rules and regulations for the construction, maintenance, and repair of buildings, including permits and penalties. That hands the question of which work needs a permit to the Florida Building Code itself, and the city adds its own gate in the fire chapter. Section 10-3.17 says a permit for construction, erection, alteration, repair, or demolition shall not be issued until the fire official, defined in § 10-3.02 as the City of Jacksonville Beach Fire Marshal or designee, has reviewed the plans and specifications and found them in compliance with Chapter 10 and the adopted edition of the FFPC. Section 10-3.03 adopts the 8th Edition of the FFPC effective June 1, 2024.
Fees and refunds follow the permit. Under § 7-19, no inspection can be made and no installation approved until all fees due under the permit and any other applicable development fees have been paid. Section 7-20(c) has the city council set the permit fee schedule by resolution, upon recommendation of the city manager. Where no work has been done under a valid permit, a written refund request filed by the holder within six (6) months of original issuance lets the building official authorize a refund of fifty (50) percent of the building permit fee on surrender of the permit; no plan check fee is refunded. Section 7-21 waives permit and inspection fees for work on tax-exempt property held and used exclusively for religious, scientific, municipal, educational, literary or charitable purposes, once the applicant files an owner affidavit and a certificate from the city tax assessor.
Signs show the same layering. Section 34-758 makes it unlawful to erect, construct, alter or maintain a sign structure without first obtaining a building permit under the Florida Building Code, separate from the sign permit. Work that departs from the plans approved by the fire official draws a written stop-work notice for that portion under § 10-3.09(b).
Violations & Fines
Under § 10-3.12(a), failure to comply with the fire chapter or a lawful order of the fire official is a misdemeanor of the second degree, punishable by a fine of not more than $500.00, or imprisonment for not more than ten (10) days, or both, and each day is a separate offense. The city can also seek an injunction or use the special magistrate process in Chapter 2, Article VI. Work that departs from the approved plans draws a written stop-work notice for that portion.
Frequently Asked Questions
Where does Jacksonville Beach say a building permit is needed?
Who reviews plans before a permit is issued?
Can I get a refund if I never start the work?
Do nonprofits pay building permit fees?
Sources & Official References
Other rules in Jacksonville Beach
Florida rules heatmap·Compare Jacksonville Beach to another location·View the Florida building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Building Permits in Nearby Cities
How other cities in this county handle building permits.