Key Facts
- Base fee
- $22 for first $1,000 of cost
- Additional fee
- $7 per extra $1,000
- Reinspection fee
- $50 per inspection
- Penalty
- Unpermitted construction doubles fees, § 4-2.8
- Director term
- 3-year mayoral appointment, § 4-3
Summary
Leominster charges twenty-two dollars for the first thousand dollars of estimated building work and seven dollars per additional thousand under Section 4-2.1, with reinspection costing fifty dollars. Section 4-2.8 doubles every fee if construction starts before a permit is obtained, and the director of inspections oversees enforcement citywide.
(a)For a total estimated cost of up to one thousand dollars, a fee of twenty-two dollars;(b)For a total estimated cost of each additional one thousand dollars or a portion thereof, a fee of seven dollars;(c)For reinspection (being not ready when called for), a fee of fifty dollars per inspection. ... (a)For failure to apply for a permit before construction has started, all fees are doubled.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 24).
Full Breakdown
1 of the Code of Ordinances. The fee for a project estimated at up to one thousand dollars is twenty-two dollars; each additional thousand dollars of estimated cost, or a portion of it, adds seven dollars; and if an inspector arrives for a scheduled inspection and the work is not ready, a fifty-dollar reinspection fee applies. 8 backs this schedule with a real deterrent: if a contractor, owner or lessee starts construction before applying for the required permit, every fee due on that project is doubled, on top of the general hundred-dollar surcharge the ordinances impose for working without required permits.
The director of inspections, appointed by the mayor for a three-year term under Section 4-3, oversees the building, wire, plumbing and gas inspectors who administer these permits, and Section 4-4 requires that churches, schools, theaters, factories, mercantile establishments and apartment houses be inspected at intervals not exceeding two years under chapter 143 of the General Laws, the City Building Code and the Zoning Ordinance. 11 demolition-delay review for historically significant resources administered by the Leominster Historical Commission.
Violations & Fines
Starting construction before a building permit issues doubles every fee owed under Section 4-2.8, and a contractor who works without any required permit at all faces a one-hundred-dollar surcharge on top of the doubled fee under Section 4-2. Demolishing a historically significant resource without the required delay-period permit under Section 4-2.11 exposes the owner to a fine under Section 1-7 for each day the violation continues, until the resource is restored.
Frequently Asked Questions
How much does a Leominster building permit cost?
What happens if I start work before getting a permit?
Who reviews and issues building permits in Leominster?
Sources & Official References
Other rules in Leominster
Compare Leominster to another location·View the Massachusetts building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.