Leominster, MA Building Safety: Plumbing Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit issuer
Board of health / inspector of plumbing
Who may pull permit
Master plumbers only
New single/two-family fee
$40 plus $5 per fixture
Commercial new construction fee
$55 plus $8 per fixture
Late-filing penalty
All fees doubled
State licensing
Registered under G.L. c. 142

Summary

Anyone doing plumbing work in Leominster must be registered or licensed by the state examiners of plumbers, and a master plumber must file a notice with the board of health and obtain an inspector-approved permit before starting, except for leak repairs. Permits carry set fees by project type, and skipping the permit before construction doubles every fee owed.

All persons who desire to engage in, carry on or work at the business of plumbing within the city shall be registered or licensed by the state examiners of plumbers in accordance with the provisions of chapter 142 of the General Laws. Every plumber before commencing work on a building shall first, except in the case of the repair of leaks, file at the office of the board of health, upon blanks provided for that purpose, a notice of the work to be performed; and no such work shall be done in any building except in accordance with plans, to be submitted if required, which shall be approved by the inspector of plumbing and a permit issued therefor. Permits to perform plumbing shall be issued to master plumbers only. ... Penalty, for failure to apply for a permit before construction has started, all fees are doubled.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 24).

Full Breakdown

c. 142. Before starting work on any building, other than repairing leaks, the plumber must file a notice of the work with the board of health on the office's prescribed forms, submit plans if the inspector of plumbing requires them, and obtain a permit; the code specifically limits issuance of plumbing permits to master plumbers, so a journeyman cannot pull the permit himself. Fees are set by project type and fixture count. New construction runs forty dollars plus five dollars per fixture for a single- or two-family home and its additions, fifty-five dollars plus eight dollars per fixture for a commercial or industrial building, and fifteen dollars plus three dollars per fixture for a church or schoolhouse.

Remodeling, repair and renovation work is billed at twenty-eight dollars plus five dollars per fixture for a single- or two-family dwelling and fifty-five dollars plus eight dollars per fixture for commercial buildings, with a flat twenty or thirty dollar charge to swap a hot water heater depending on the building type. A reinspection costs fifty dollars per visit, a residential backflow preventer permit is thirty-eight dollars, and a written opinion from the inspector costs thirty dollars plus thirty dollars for any related inspection. The section carries its own penalty: if a permit application is not filed before construction has already started, every fee on the job is doubled.

Plumbing connects to the city's separate sewer-connection rule in § 17-4, which requires an independent connection to the public sanitary sewer unless the board of health finds that infeasible.

Violations & Fines

Working without a state plumbing license or without a Leominster permit exposes a plumber to enforcement by the board of health and the inspector of plumbing, and under the section's own penalty clause every listed fee is doubled when a permit is filed only after construction has already begun. The city's general penalty at § 1-7 caps citywide fines at three hundred dollars per offense where a chapter states no separate penalty.

Frequently Asked Questions

Do I need a permit to repair a leaking pipe in Leominster?
No. Section 17-3 exempts leak repairs from the pre-work notice and permit filing required for other plumbing jobs, though the plumber performing the repair still must be registered or licensed by the state examiners of plumbers under G.L. c. 142. Any rearrangement of pipes or fixtures beyond a straightforward leak repair falls back under the full permit requirement.
Who can legally pull a plumbing permit in Leominster?
Only a master plumber. Section 17-3 states permits to perform plumbing shall be issued to master plumbers only, so a journeyman plumber working under a master's supervision cannot apply for or hold the permit himself; the master plumber of record remains responsible for the filed job.
What happens if I start plumbing work before getting a permit?
Section 17-3's penalty clause doubles every fee for the job, including the base permit charge and the per-fixture charges, when the application is filed after construction has already started. There is no separate criminal fine written into this section beyond the doubled fee.

Sources & Official References

Other rules in Leominster

All Leominster rules

Compare Leominster to another location·View the Massachusetts building safety overview

Get notified when Plumbing Permits in Leominster, MA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.