Key Facts

Zoning permit issuer
Land Use Administrator/Zoning Officer (AZO)
Relationship to building permit
Zoning permit is required in addition to a building permit
Unlisted building permit fee
$72 under Schedule II
Flood hazard determination fee
$15 from the Township Engineer's office
Fine range
$100 to $1,000, or up to 90 days in county jail
Abatement notice
10 days' written notice from the AZO

Summary

In Monroe Township, Middlesex County, a zoning permit from the Land Use Administrator/Zoning Officer is required before any building that skips Planning Board or Zoning Board of Adjustment review is erected, constructed, structurally altered or enlarged. Section 30-3 says the zoning permit is required in addition to a building permit.

I. The AZO shall be responsible for the issuance of a zoning permit. A zoning permit shall be required prior to the erection, construction, structural alteration or enlargement of any building which does not require Planning Board or Zoning Board of Adjustment review and approval pursuant to either the Municipal Land Use Law (N.J.S.A. 40:55D-1 et seq.) or the development regulations of Monroe Township. A zoning permit shall be required in addition to a building permit. No zoning permit shall be issued by the AZO unless the proposed improvement is in conformance with the development regulations, codes and ordinances of Monroe Township.

Full Breakdown

Two approvals sit in front of construction in Monroe Township, Middlesex County. The first is the zoning permit. Under § 30-3, the Land Use Administrator/Zoning Officer, called the AZO in the Code, issues it before the erection, construction, structural alteration or enlargement of any building that does not need Planning Board or Zoning Board of Adjustment review and approval. The second is the building permit, and § 30-3 states the zoning permit is required in addition to it. The AZO issues no zoning permit unless the proposed improvement conforms to the development regulations, codes and ordinances of Monroe Township. Section 30-2 puts the AZO's office in the Municipal Complex, open to the public during normal business hours.

Building permits themselves run through the State Uniform Construction Code Enforcing Agency created by § 25-1, with the Construction Official as chief administrator and building, plumbing, electrical and fire protection subcode officials. Section 20-1 adopts the code governing the construction, alteration, addition, repair, removal, demolition, use, location, occupancy and maintenance of buildings and structures. Fees follow Chapter 39 under § 25-2, and Schedule II prices a building permit not otherwise listed at $72. Section 25-4 describes the enforcing agency fee as covering plan review, construction permit, certificate of occupancy, demolition permit, moving of building permit, elevator permit and sign permit.

Other gates apply before a permit issues. Section 20-3 requires a flood hazard area determination from the office of the Township Engineer, for a $15 fee, before new construction, alterations or additions. Where tree removal is part of the job, § 97-5 A(2) provides that no building permit issues until the applicant, unless exempt, has obtained any permit required under the tree chapter. Section 25-3 waives permit fees for accessibility improvements to a disabled person's own living unit.

Violations & Fines

Section 30-6 A sets a fine of not less than $100 nor more than $1,000 or imprisonment in the county jail for up to 90 days, at the discretion of the Municipal Court, and each day the violation continues after notice and a reasonable opportunity to cure is a separate violation. Under § 30-4 A, the owner, tenant, architect, building contractor or anyone who takes part in or assists is guilty. Section 30-5 lets the AZO order abatement on 10 days' notice and issue a summons.

Frequently Asked Questions

Do I need a zoning permit as well as a building permit in Monroe Township?
Yes, for any building that does not require Planning Board or Zoning Board of Adjustment approval. Section 30-3 states that a zoning permit shall be required in addition to a building permit, before the erection, construction, structural alteration or enlargement of the building. The AZO issues it only if the project conforms to Township codes.
Who handles building permits in Monroe Township?
The State Uniform Construction Code Enforcing Agency under § 25-1, led by the Construction Official as chief administrator. Building, plumbing, electrical and fire protection subcode officials work under it. The public has the right to do business with the agency at one office location, except for emergencies.
What does a building permit cost if it is not on the fee schedule?
Schedule II in Chapter 39 states that the fee for the issuance of a building permit that is not listed is $72. Section 25-2 ties all Construction Office fees to Chapter 39, and § 25-3 waives fees for accessibility improvements to a disabled person's own living unit.
Does tree removal affect my building permit?
Yes. Section 97-5 A(2) says that where tree removal is for construction of a building, driveway, recreation area or anything else requiring a building permit, no building permit issues until the applicant, unless exempt, has obtained any permit required under the tree chapter. Tree removal permits are issued by the Conservation Officer.

Sources & Official References

Other rules in Monroe Township (Middlesex County)

All Monroe Township (Middlesex County) rules

Compare Monroe Township (Middlesex County) to another location·View the New Jersey building safety overview

Get notified when Building Permits in Monroe Township (Middlesex County), NJ changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in this county handle building permits.

Edison, NJ
Some Restrictions