Application expiration
180 days from receipt unless extended
Extension limit
90-day increments, up to 10 extensions
Permit validity
Void if no inspection within 1 year
Enforcing officer
City Building Official
Penalty
Misdemeanor, fine under § 1-1.06
Adopted code
2025 California Building Code (Jan. 1, 2026)

Summary

Building permit applications in Monterey expire 180 days after the city receives them unless the Building Official grants an extension, and any project authorized by an issued permit must pass a required inspection within one year of issuance or the permit becomes void. Extensions run in 90-day increments, capped at ten.

a.Section 105.3.2 is amended to read as follows:105.3.2 Time limitation of application. An application for a permit for proposed work shall expire 180 days from the date of receipt of the application unless extended by the Building Official pursuant to this section. An applicant may request that the Building Official extend the expiration date of the permit application upon a showing of circumstances beyond the applicant’s control that have prevented permit issuance. Applicant’s request for an extension must be made in writing to the Building Official prior to the permit application’s expiration date with the payment of any applicable fees. The Building Official may extend the expiration date in 90 day increments no more than 10 times, upon a finding that circumstances beyond the applicant’s control prevented permit issuance.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 3721, passed July 7, 2026).

Full Breakdown

1), then amends the Code's own administrative permit provisions to fit local practice. 2, an application for a building permit expires 180 days after the Building Official's office receives it unless the Official grants an extension. A property owner who needs more time must ask in writing before the application lapses and pay any applicable fee; the Building Official can then push the deadline back in 90-day increments, but never more than ten times, and only on a showing that circumstances outside the applicant's control held up permit issuance.

3 of the 2025 Building Code, or the permit itself expires and becomes null and void; work cannot continue under an expired permit, and a brand-new application with new fees is required to pick the project back up. 1(b)-(c)). 2). 06, enforceable through the City's Administrative Remedies Ordinance, with each day a violation continues counting as a separate offense (§ 9-66).

Violations & Fines

Working past an expired permit, letting a building permit application sit idle past 180 days without a written extension request, or failing to secure at least one required inspection within a year of issuance are Chapter 9 violations. Each is a misdemeanor under § 9-66, fined per § 1-1.06, enforceable through the City's Administrative Remedies Ordinance, and each day the violation continues is a separate offense; the City may also abate it as a public nuisance.

Frequently Asked Questions

How long is a Monterey building permit application valid before it expires?
Under Monterey City Code § 9-1(a), a building permit application expires 180 days after the Building Official's office receives it. You can ask in writing for more time before that deadline, and the Building Official may grant extensions in 90-day increments, up to ten times, if circumstances beyond your control delayed permit issuance.
What happens if my Monterey building permit sits without an inspection?
Once issued, the permit becomes null and void if the project has not passed at least one required inspection within one year of issuance, under § 9-1(b). You cannot keep working under an expired permit; you must file a brand-new application and pay the applicable fees again.
Which building code does Monterey enforce for permits?
Monterey adopted the 2025 California Building Code and 2025 California Residential Code, effective for applications filed on or after January 1, 2026, under Monterey City Code § 9-0.1. Applications complete before that date are grandfathered to the prior code cycle under § 9-0.2.

Sources & Official References

Other rules in Monterey

All Monterey rules

California rules heatmap·Compare Monterey to another location·View the California building safety overview

Get notified when Building Permits in Monterey, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.