Palm Springs, CA Building Safety: Building Permits (2026)
Key Facts
- Governing code
- 2025 California Building Code, adopted § 8.04.010
- Application abandonment
- 180 days after filing without good-faith pursuit
- Application extension
- Up to two 90-day extensions on written request
- Permit expiration
- Work must start within 12 months of issuance
- Progress lapse
- 180 days without a passed inspection voids permit
- Maximum permit term
- 3 years unless City Council extends for cause
- Appeal deadline
- 10 days to file with Building Code Board of Appeals
Summary
Palm Springs adopts the 2025 California Building Code by reference under Municipal Code § 8.04.010, and the Department of Building and Safety enforces it. Under § 8.04.015, a building permit application is deemed abandoned 180 days after filing unless pursued in good faith, and every issued permit becomes invalid if work is not commenced within 12 months or is halted for 180 days.
These certain documents, a copy of each of which are on file in the office of the city clerk, being marked and designated as the 2025 California Building Code, California Code of Regulations Title 24, Part 2, Volumes 1 and 2, including Chapter 1, Appendices C, I and J, and all tables and indices thereto, except as hereinafter modified, are hereby adopted by reference, pursuant to Section 50022.1 et seq., of the California Government Code. ... 105.3.2 Time limitation of application. ... An application for a permit for any proposed work shall be deemed to have been abandoned 180 days after the date of filing, unless such application has been pursued in good faith or a permit has been issued; except that the building official is authorized to grant one or two extensions of time for additional periods not exceeding 90 days each. ... 105.5 Expiration. ... Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 12 months after its issuance, or if the work authorized on the site by such permit is suspended, abandoned, or without progress at any time after the work is commenced for a period of 180 days.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4923139; v14 updated 2026-06-24).
Full Breakdown
04, Article I. 1 et seq. 015 then layers on local amendments to the permit process itself. An application for a permit is deemed abandoned 180 days after filing unless the applicant has pursued it in good faith or a permit has already issued; the building official can grant one or two extensions of up to 90 days each on a written request showing justifiable cause, and anyone who lets the extension window lapse must resubmit plans and pay a new plan review fee under the laws in effect at that later date.
Once issued, a permit becomes invalid if work at the site is not commenced within 12 months, or if it is suspended, abandoned, or without progress for 180 days; progress specifically means passing at least one inspection required under Section 110. The building official can extend an unexpired permit up to 90 days at a time on a written showing of circumstances beyond the applicant's control, but no permit can run past three years from issuance without City Council authorization for significant cause. A separate exception lets code-enforcement permits carry expiration dates shorter than 180 days at the building official's discretion.
Disputes over a Building and Safety decision go to the three-member Building Code Board of Appeals: an aggrieved person files a written notice of appeal within ten days of the action, pays the Department's appeal fee set by City Council resolution, and the Board must hear the appeal within 45 days.
Violations & Fines
Building without a required permit, or letting one lapse and continuing work, exposes an owner to code enforcement action by the Department of Building and Safety, including stop-work orders and separate permit fees for after-the-fact approval. Work started under an expired permit must be re-permitted from scratch; there is no grace period once the 12-month commencement window or the 180-day progress window closes, and the file must show a passed Section 110 inspection to prove progress.
Frequently Asked Questions
How long do I have to start work after getting a Palm Springs building permit?
What happens if my building permit application sits too long before I pull the permit?
Can a Palm Springs building permit be extended past its normal term?
Sources & Official References
Other rules in Palm Springs
California rules heatmap·Compare Palm Springs to another location·View the California building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Building Permits in Nearby Cities
How other cities in Riverside County handle building permits.