Inspection 1
Pre-Gunite: steel placed and bonded before gunite
Inspection 2
Underground: utilities in before pipes are covered
Inspection 3
Deck bonding: before deck concrete is poured
Inspection 4
Encapsulation: before plaster, alarms/barriers must be in place
Inspection 5
Final: after all stages pass and pool is filled
Governing section
Municipal Code § 8.04.015, CBC § 110.3.13

Summary

Swimming pool construction in Palm Springs runs through five mandatory inspections spelled out in Municipal Code § 8.04.015, which adds subsection 110.3.13 to the adopted California Building Code. A pool permit holder must pass Pre-Gunite, Underground plumbing/gas/electrical, Deck bonding, Encapsulation and a Final inspection, in that order, before the pool can be filled and used.

110.3.13 Swimming pools. The minimum inspection requirements for swimming pool permits are as listed. 110.3.13.1 Pre-Gunite. Inspection shall be made after all pool steal is in place and bonded but prior to application of any gunite. 110.3.13.2 Underground plumbing, gas and electrical. Inspection shall be made after the Pre-Gunite and installation of all underground utilities, but prior to covering any pipes or conduits. Note: A single Combination Inspection may be performed which includes Pre-Gunite and Underground. 110.3.13.3 Deck bonding. Inspection shall be made after the pool deck steel is installed and bonded, but prior to pouring any concrete. 110.3.13.4 Encapsulation. Inspection shall be made after the pool is gunited, and the lighting niche is installed and wired, but prior to the application of plaster or other finishes. All alarms, barriers and other protective measures must be in place. 110.3.13.5 Final. Inspection shall be made after all work has been inspected and complete and the pool is filled with water.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4923139; v14 updated 2026-06-24).

Full Breakdown

015, sets the minimum inspection sequence for every swimming pool permit issued by the Department of Building and Safety. The Pre-Gunite inspection comes first, after the pool steel is placed and bonded but before any gunite is sprayed. Next is the Underground inspection, covering plumbing, gas and electrical lines, which happens after Pre-Gunite and after all underground utilities are installed but before any pipe or conduit is covered; the code allows a single combination inspection to cover both Pre-Gunite and Underground at once. Deck bonding follows once the pool deck steel is installed and bonded but before any deck concrete is poured.

The Encapsulation inspection comes after the shell is gunited and the lighting niche is installed and wired, but before plaster or any other finish goes on, and by that point every alarm, barrier and other protective safety measure required for the pool must already be in place, not added later. The Final inspection closes out the permit only after every prior inspection has passed and the pool has been filled with water, confirming the completed system holds and operates as built. Skipping a stage, such as pouring gunite before Pre-Gunite sign-off or plastering before Encapsulation approval, forces the contractor to expose the covered work again so the inspector can verify it, tearing out whatever finish or concrete was poured over it.

Violations & Fines

Pouring gunite, covering underground lines, pouring deck concrete or applying plaster before the corresponding inspection has passed is a permit violation the Department of Building and Safety enforces by requiring the covering material to be removed so the concealed work can be inspected. A pool filled with water before the Final inspection, or operated before required alarms and barriers are installed and verified at the Encapsulation stage, also violates § 110.3.13 and can hold up the certificate of occupancy or final sign-off on the permit.

Frequently Asked Questions

What is the first inspection required for a new pool in Palm Springs?
The Pre-Gunite inspection under Municipal Code § 8.04.015. It happens after all the pool's steel reinforcement is in place and bonded, but before any gunite is sprayed onto the shell. Skipping straight to gunite without this sign-off from the Department of Building and Safety violates the pool inspection sequence.
Can Palm Springs combine the pre-gunite and underground pool inspections?
Yes. Section 110.3.13.2 allows a single combination inspection covering both the Pre-Gunite step and the Underground plumbing, gas and electrical step, as long as it happens after the steel is bonded and all underground utilities are installed but before any pipe or conduit gets covered up.
Do pool alarms and barriers need to be installed before the pool is finished?
Yes. Section 110.3.13.4 requires all alarms, barriers and other protective safety measures to be in place by the Encapsulation inspection, which happens after the shell is gunited and the lighting niche is wired but before plaster or any other finish is applied, well before the Final inspection and filling.

Sources & Official References

Other rules in Palm Springs

All Palm Springs rules

California rules heatmap·Compare Palm Springs to another location·View the California building safety overview

Get notified when Building Inspections in Palm Springs, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Nearby Cities

How other cities in Riverside County handle building inspections.

Corona, CA
Some Restrictions
Moreno Valley, CA
Some Restrictions
Temecula, CA
Some Restrictions
Riverside, CA
Some Restrictions