Key Facts

Governing section
§ 152.03 Building Permits
Underlying code
Florida Building Code, adopted § 152.01
Issuing office
City Building Department
Permit expiration rule
FBC § 104.9.3, per § 152.04
Shell permits allowed
Yes, exterior/roof/common areas only
Liability
Applicant and owner jointly responsible

Summary

Pompano Beach requires a construction permit from the Building Department for every phase of a construction project before work begins, under Code of Ordinances § 152.03. Plans, a qualified applicant's signature, and the permit fee must all be submitted together before an inspector approves the work.

The Building Department shall issue construction permits, as required by Section 104 of the Florida Building Code, hereinafter referred to as permits, to the owner or agent acting on behalf of the owner for all phases of a construction project upon completion of the following requirements. (1) Plans and specifications for all phases of the construction project shall be submitted at the same time in accordance with Section 104.6.2 of the Florida Building Code. (2) Each application for permitting of the construction project must be submitted at the same time and shall bear the signatures of the qualified applicant, in accordance with Section 104.6 of the Florida Building Code, and bear the seal of a Notary Public, including the owner's signature, where applicable.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-122: Supplement contains: Local legislation current through 2026-35, passed 7-29-26).

Full Breakdown

03 sets the local procedure for getting a permit under it. The Building Department issues construction permits, defined as written authorization from the Building Official to proceed with construction, alteration, repairs, installation or demolition, listing every contractor authorized to work on the job. 2. 2. 06(D). 03(D) makes clear the section cannot be read to repeal or restrict FBC requirements. 3's timelines, so an inactive permit can lapse and force a fresh application.

Violations & Fines

Working without an issued permit, or contrary to Section 104 of the Florida Building Code, is a violation of § 152.01. Each day a violation continues is a separate offense; conviction can bring a fine, imprisonment, or both, per the general penalty provision at § 10.99. The Building Official may also issue a stop-work order that stays in effect until compliance is achieved, as authorized under the related § 152.06(G).

Frequently Asked Questions

What has to be submitted before Pompano Beach issues a building permit?
Plans and specifications for every phase of the project submitted together, a signed and notarized application identifying a qualified applicant, and payment of the permit fee, per § 152.03(C). The application and plans are then examined together to confirm compliance with state and local law before any inspector approves the work.
Can I get a permit for just the shell of a building in Pompano Beach?
Yes. Section 152.03(C)(7) lets a qualified applicant file separate permits for a building proposed as a 'shell' of exterior walls, roof and common areas, but no work on any other phase may start until its own permit is issued, even after the shell certificate of completion is granted.
How long is a Pompano Beach building permit valid?
Permit expiration follows Section 104.9.3 of the Florida Building Code as applied through § 152.04 of the city code. Once a permit lapses under that FBC timeline, the applicant must reapply before resuming work.
Who is responsible if permitted work does not comply with the code?
The permit applicant and the property owner are jointly and severally responsible for compliance, a standard the code states directly for related debris-mitigation permits at § 152.06(D) and that applies to the permitting scheme generally.

Sources & Official References

Other rules in Pompano Beach

All Pompano Beach rules

Florida rules heatmap·Compare Pompano Beach to another location·View the Florida building safety overview

Get notified when Building Permits in Pompano Beach, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in Broward County handle building permits.