Key Facts

Permit required for
Erection, construction, alteration, addition
Issuing office
Director of Building and Safety
Min. residential frontage
30 feet on dedicated street
Flood hazard appeal path
Planning Commission, then City Council
Minor work exempt
Fences <=6 ft, retaining walls <=3 ft
Violation classification
Misdemeanor, separate offense per day

Summary

In Redlands, California, no property owner or authorized agent may begin erecting, constructing, reconstructing, moving, converting or adding to any building without first securing a building permit from the Director of Building and Safety. The city withholds permits for work that would conflict with the zoning title, invalidate the general plan, or serve a residential lot lacking the required thirty-foot street frontage on a dedicated street.

It is unlawful for any property owner, or his authorized agent, to commence any work pertaining to the erection, construction, reconstruction, moving, conversion or alteration of any building, or any addition to any building, until a building permit has first been secured from the director of building and safety for such work.

Full Breakdown

Redlands City Code section 18.188.010 makes it unlawful to commence erection, construction, reconstruction, moving, conversion or alteration of any building, or an addition to one, before a building permit is secured from the Director of Building and Safety. Section 18.188.020 requires the application itself to go on a printed form from the Department of Building and Safety, accompanied by accurate lot dimensions, the size and location of existing buildings, and the dimensions of all yards and open spaces; the department can demand a licensed surveyor's survey if existing records are incomplete, and the original application stays on file at the department.

Issuance is restricted in several ways. Section 18.188.030 voids any permit that does not conform to the zoning title, an approved site plan, or a conditional use permit. Section 18.188.040 bars a permit that would deprive neighboring property owners of the use of their land or invalidate the general plan. Section 18.188.050 requires a minimum thirty-foot (30') lot frontage on a dedicated street or way for a residential building permit, with hillside lots referred instead to section 18.152.020. Section 18.188.060 requires the applicant to dedicate any undedicated half streets or additional right-of-way shown on the general plan, up to a thirty-foot half street on a sixty-foot right-of-way. Section 18.188.070 requires the applicant to install street paving, curbs, gutters and sidewalks abutting the lot. Section 18.188.080 lets the Director of Building and Safety refuse a permit where the lot is a flood hazard, appealable to the Planning Commission and then the City Council. Separately, section 15.04.020 of the adopted 2025 California Building Code exempts limited work from a permit altogether, including fences up to six feet, masonry or concrete fences up to three feet, retaining walls up to three feet, and flagpoles up to thirty feet on residential lots.

Violations & Fines

Building without a required permit, or building contrary to a permit's terms, is an unlawful public nuisance under Redlands City Code section 18.208.040, and the City Attorney may sue to abate it on Council order. Section 18.208.050 makes any violation of Title 18, including its building permit chapter, a misdemeanor, with each day the violation continues charged as a separate offense.

Frequently Asked Questions

Do I need a permit to build a fence in Redlands?
Not always. City Code section 15.04.020 exempts wood, chain-link, plastic, vinyl or metal fences up to six feet, and masonry or concrete fences up to three feet, provided the fence does not serve as a required swimming pool enclosure under section 15.06.080.
What documents do I need to apply for a building permit?
Section 18.188.020 requires a printed application from the Department of Building and Safety showing accurate lot dimensions, the size and location of existing buildings, and the dimensions of all yards and open spaces; a licensed surveyor's survey may be required if records are incomplete.
Can the city refuse my building permit for a flood-prone lot?
Yes. Section 18.188.080 authorizes the Director of Building and Safety to refuse a permit where the lot is a flood hazard to the proposed or adjacent structures; the applicant may appeal to the Planning Commission and then the City Council.
Does the city require street work before issuing a building permit?
Yes. Section 18.188.060 requires dedication of any undedicated half streets or right-of-way shown on the general plan, and section 18.188.070 requires installing street paving, curbs, gutters and sidewalks abutting the lot before the permit is used.

Sources & Official References

Other rules in Redlands

All Redlands rules

California rules heatmap·Compare Redlands to another location·View the California building safety overview

Get notified when Building Permits in Redlands, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in San Bernardino County handle building permits.

Hesperia, CA
Some Restrictions
Fontana, CA
Some Restrictions
Rancho Cucamonga, CA
Some Restrictions
Victorville, CA
Some Restrictions
Rialto, CA
Some Restrictions
Ontario, CA
Some Restrictions
Chino, CA
Some Restrictions
San Bernardino, CA
Some Restrictions