Richland, WA Building Safety: Building Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit required
For erecting, moving, adding to or altering any structure
Annual permits
Not adopted; every project needs its own permit
Contractor requirement
Richland business license plus WA L&I registration
Fee basis
1997 UBC Table 1-A valuation, updated each January 1
Small shed exemption
≤200 sf (IRC)/120 sf (IBC) needs placement permit only
Appeals
Mid-Columbia Board of Appeals, RMC § 21.01.020(I)

Summary

In the City of Richland, Washington, RMC § 23.70.030 bars erecting, moving, adding to or structurally altering any building or structure without a permit issued under the city's adopted building code, and bars issuing that permit unless the project also conforms to Title 23 zoning. Richland does not offer annual or blanket permits, and contractors need both a city business license and state registration before starting work.

No building or other structure shall be erected, moved, added to, or structurally altered without a building permit issued in accordance with the building code of the city of Richland. No building permit shall be issued except in conformity with the provisions of this title.

Full Breakdown

Section 23.70.030, in the zoning title's enforcement chapter, sets the baseline: no building or other structure in Richland can be erected, moved, added to, or structurally altered without a building permit issued under the city's building code, and the administrative official cannot issue that permit unless the proposal also satisfies Title 23's zoning standards. RMC § 21.01.020 layers Richland's own amendments onto the adopted International Building and Residential Codes' Chapter 1. Subsections B and C strike the model code's annual-permit option entirely: Richland does not issue or recognize annual permits or annual permit records.

Subsection D exempts only a narrow set of small accessory structures, tool and storage sheds and playhouses no larger than 200 square feet (IRC) or 120 square feet (IBC), and certain amusement-ride structures, from needing a full building permit; those still need a no-fee location placement permit before construction. Subsection E requires every contractor and subcontractor to hold a current City of Richland business license under Title 5 and a current Washington State Department of Labor and Industries contractor registration before any actual construction work begins.

Permit fees under Subsection F are calculated from Table 1-A of the 1997 Uniform Building Code applied to the greater of the declared construction valuation or the city's Supplemental Table 1-B, updated every January 1st; plan review runs 65 percent of the building permit fee, with no plan-review fee at all for single-family or duplex construction unless plans change after approval. Disputes over a permit decision go to the Mid-Columbia Board of Appeals under RMC § 21.01.020(I), the joint board Richland shares with Kennewick, Pasco, West Richland, Benton County and Franklin County.

Violations & Fines

RMC § 23.70.270 makes building without the required permit a civil infraction under RMC § 10.02.050(E). A third infraction for the same or similar conduct at the same location escalates to a criminal misdemeanor under RMC § 1.30.010. Each day the unpermitted work or use continues is a separate offense, and violations tied to RMC § 23.42.030 are declared a public nuisance the city attorney can abate civilly.

Frequently Asked Questions

When does Richland require a building permit?
RMC § 23.70.030 requires a permit before erecting, moving, adding to, or structurally altering any building or structure in the city, and the permit cannot be issued unless the project also meets Title 23's zoning rules.
Can I get one annual permit for repeat work in Richland?
No. RMC § 21.01.020(B) and (C) specifically decline to adopt the model code's annual permit and annual permit records provisions, so Richland does not issue or honor them.
Does my contractor need a special license to pull a Richland permit?
Yes. RMC § 21.01.020(E) requires every contractor and subcontractor to hold a current City of Richland business license under Title 5 and a current Washington State Department of Labor and Industries contractor registration before starting construction.
What happens if I build without a permit in Richland?
RMC § 23.70.270 treats it as a civil infraction under RMC § 10.02.050(E); a third violation for similar conduct at the same site becomes a misdemeanor under RMC § 1.30.010, and continuing violations accrue as separate daily offenses.

Sources & Official References

Other rules in Richland

All Richland rules

Compare Richland to another location·View the Washington building safety overview

Get notified when Building Permits in Richland, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in Benton County handle building permits.

Kennewick, WA
Light Restrictions