Salem, OR Building Safety: Building Permits (2026)
Key Facts
- Governing section
- SRC 56.007
- Application abandons after
- 180 days without pursuit
- Extension allowed
- one, up to 180 more days
- Permit validity
- 24 months from issuance
- Civil penalty
- up to $5,000 per violation per day
- Reinstatement window
- within one year of expiration
Summary
Salem requires a building permit before any work covered by the State Building Code begins, under Salem Revised Code 56.007. The Building Official reviews the application and plans, issues the permit once the project complies and fees are paid, and can grant phased permits for large projects. Unpursued applications lapse after 180 days.
(a)A person shall, prior to undertaking or causing to be undertaken any work for which a permit is required under any provision of the Building Code, obtain a building permit as provided in this section. ... (c)An application for a building permit shall be deemed abandoned 180 days after the date of filing, unless the applicant continues to pursue the application in good faith. The Building Official may grant not more than one extension, for an additional period not to exceed 180 days. The applicant must request the extension, in writing, setting forth good and sufficient cause for the extension to the satisfaction of the Building Official prior to the date the application is deemed abandoned pursuant to this subsection.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 26 Update 1).
Full Breakdown
SRC 56.007 requires anyone doing work regulated by the Building Code (structural, residential, mechanical, plumbing, electrical, energy or manufactured-home specialty codes under SRC 56.001) to obtain a building permit before starting. The Building Official, and other City departments as needed, reviews the application, plans, specifications and computations for compliance before issuing the permit, and endorses the approved plans in writing or by stamp; all work must match those approved plans unless the Building Official authorizes a change. One approved set stays on the job site at all times while work is underway.
An application is deemed abandoned 180 days after filing unless the applicant keeps pursuing it in good faith; the Building Official may grant one extension of up to 180 additional days if the applicant requests it in writing with good cause before the abandonment date (SRC 56.007(c)). For large projects, the Building Official may issue phased permits covering part of a building before the full plan set is approved, though approval of a later phase is never guaranteed (SRC 56.007(f)).
Once issued, a building permit expires 24 months from the issue date unless the work has passed final inspection; the Building Official can approve a longer period for large or complex projects, but any lapsed permit requires a new one for the unfinished work (SRC 56.013). A permit holder may request a single 180-day extension before expiration (SRC 56.014(a)), and an expired permit can be reinstated within one year if the code hasn't changed and the plans stay the same (SRC 56.014(b)). Starting work without a permit triggers a mandatory investigation fee on top of the permit fee, whether or not a permit is later issued (SRC 56.015).
Violations & Fines
Working without a required permit, ignoring a stop work order, or making false statements on a permit application are all prohibited under SRC 56.195 and can each draw a civil penalty of up to $5,000, with every additional day of noncompliance counted as a separate violation (SRC 56.198(e)). The City withholds a Notice of Final Completion until any violation is cured and the penalty paid, and may seek injunctive relief for willful violations.
Frequently Asked Questions
Does Salem require a permit for home renovations?
How long can a Salem building permit application sit before it expires?
How long is an issued Salem building permit good for?
What happens if I build in Salem without a permit?
Sources & Official References
Other rules in Salem
Compare Salem to another location·View the Oregon building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.