Key Facts

Permit required for
Construction, alteration, demolition, occupancy change
Application lapses
6 months after filing without issuance
Issued permit expires
If work not started within 6 months
No-permit penalty
100% of the usual permit fee
Permit posting
Within 5 ft of right-of-way, visible
Citation
City Code Sec. 105-46

Summary

In Sandy Springs, anyone who wants to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or install, alter, or replace an electrical, gas, mechanical, or plumbing system, must first apply to the building official and obtain a permit before starting work, under City Code Sec. 105-46(a)(1).

(a)Permit application.(1)Changed occupancy. When required, any owner, authorized agent, or con-tractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert, or replace any electrical, gas, mechanical, or plumbing system, the installation of which is regulated by the construction codes, or to cause any such work to be done, shall first make application to the building official and obtain the required permit for the work. ... (g)(2)Work commencing before permit issuance. Any person who commences any work on a building, structure, electrical, gas, mechanical, or plumbing, system before obtaining the necessary permits are subject to a penalty of 100 percent of the usual permit fee in addition to the required permit fees.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 24 | Development Code: Supplement 2 | Technical Manuals: Supplement 4).

Full Breakdown

City Code Sec. 105-46 governs when a building permit is required and what an applicant must do to get one. Anyone who wants to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install, alter, remove, convert, or replace an electrical, gas, mechanical, or plumbing system regulated by the construction codes, must first apply to the building official and obtain the permit before doing the work. The application must include the required fee, a general description of the work and its location, and be signed by the owner or an authorized agent; the building official can require drawings and specifications for work of any complexity.

Ordinary minor repairs may proceed without a permit if the building official approves and the repair does not violate the construction codes. A permit application is deemed abandoned six months after filing if no permit has issued, though the building official can grant one or more 90-day extensions on written request showing justifiable cause. Once issued, a permit itself becomes invalid if the authorized work is not started within six months, or is suspended or abandoned for six months after starting, subject to the same 90-day extension process.

Anyone who begins work before obtaining the necessary permit is subject to a penalty equal to 100 percent of the usual permit fee, on top of the fee itself. Permit holders must post the permit card within five feet of the right-of-way, roughly five feet above grade and facing the street, and keep it there until the certificate of occupancy or completion issues. Contractors performing the work must supply their state license number to the city before a permit issues, and the building official can revoke a permit for a false statement in the application or for work that violates the construction codes.

Violations & Fines

Starting work before a permit issues triggers a penalty of 100 percent of the standard permit fee in addition to the fee itself, under Section 105-46(g)(2). The building official can issue a stop work order under Section 105-45(c) for work done without a permit or contrary to the Code, and can revoke an issued permit under Section 105-45(d) for a false statement in the application or for work that violates the construction codes.

Frequently Asked Questions

When does Sandy Springs require a building permit?
A permit is required before anyone constructs, enlarges, alters, repairs, moves, demolishes, or changes the occupancy of a building or structure, or installs, alters, or replaces an electrical, gas, mechanical, or plumbing system covered by the construction codes. The application, including the required fee, a general work description, and the owner's or agent's signature, must be filed with the building official before work starts, under Section 105-46(a)(1).
What happens if I start construction before getting a permit?
Section 105-46(g)(2) imposes a penalty equal to 100 percent of the usual permit fee, charged on top of the fee itself, on anyone who commences work before obtaining the necessary permit. The building official can also issue a stop work order under Section 105-45(c) ordering the work to cease immediately.
How long is a Sandy Springs building permit valid once issued?
The permit becomes invalid if the authorized work is not started within six months of issuance, or if it is suspended or abandoned for six months after starting. The building official can grant one or more extensions of up to 90 days each if the permit holder requests one in writing and shows justifiable cause, under Section 105-46(f)(1).

Sources & Official References

Other rules in Sandy Springs

All Sandy Springs rules

Compare Sandy Springs to another location·View the Georgia building safety overview

Get notified when Building Permits in Sandy Springs, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in Fulton County handle building permits.

Atlanta, GA
Some Restrictions
Roswell, GA
Some Restrictions