Santa Fe, NM Building Safety: Building Permits (2026)
Key Facts
- Permit required for
- construction, erection or demolition
- Residential permit life
- 1 year from issuance
- Commercial permit life
- 2 years from issuance
- Base administrative fee
- $40.00 per permit
- No-permit penalty
- double the original fee
- Extension fee
- $100.00 per six months
Summary
No structure in Santa Fe can be built, erected or demolished without a building permit under Section 7-1.5(A) SFCC 1987, and the work must comply with every adopted code listed in Section 7-1.1(A). Residential permits expire one year after issuance and commercial permits after two, per Section 7-1.6, and building without a permit doubles the fee owed.
A.Except as otherwise provided in this Code, no building permit shall be issued for the construction, erection or demolition of any structure of any kind within the planning and platting jurisdiction of the city unless the construction, erection or demolition of such structure complies with the terms and provisions of the codes as set forth in Section 7-1.1A. SFCC 1987 and all applicable ordinances adopted by the city.B.Additional provisions regarding building permits are set forth in Section 14-3.10 SFCC 1987.
Full Breakdown
1A. SFCC 1987 and all applicable ordinances adopted by the city. 10 SFCC 1987, the Land Development Code's permitting article. 6 sets residential construction permits to expire one year from issuance and commercial construction permits to expire two years from issuance, with grading, drainage, landscape and utility infrastructure permits also running two years regardless of whether the underlying project is residential or commercial. The governing body may temporarily suspend that expiration clock by resolution during a broad economic downturn, but the section bars using that suspension power for an individual project or owner's situation. 00 administrative fee on every permit.
Violations & Fines
Building, erecting or demolishing a structure without the required permit is enforceable under Sections 1-3 and 14-11 SFCC 1987 through Section 7-1.1(B), and Table 7-1.11-1 doubles the original permit fee for anyone who builds without first obtaining one. Letting a residential permit run past its one-year expiration, or a commercial permit past two years, requires a new extension application and the $100.00 six-month extension fee listed in the same fee table.
Frequently Asked Questions
Do I need a permit to build or demolish a structure in Santa Fe?
How long is a Santa Fe building permit valid?
What is the penalty for building without a permit in Santa Fe?
Sources & Official References
Other rules in Santa Fe
Compare Santa Fe to another location·View the New Mexico building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.