Key Facts

Adopted code
2020 NM Electrical Code (NEC), NMAC 14.10.4
Permit issuance fee
$40.00 flat
Residential 100-amp meter loop fee
$45.00
Commercial over-2,000-amp panel fee
$900.00
No-permit penalty
double the original fee
Records on file at
office of building inspections

Summary

Santa Fe enforces electrical work through the 2020 New Mexico Electrical Code, adopted by reference in Section 7-1.1(A)(14) SFCC 1987, which incorporates the National Electrical Code as amended by the state construction industries division. A permit and a $40 issuance fee are required before wiring work begins, with panel-specific fees added under Table 7-1.11-1.

A.For the purpose of regulating the erection, construction, enlargement, alteration, repair, moving, removal, conversion, demolition, occupancy, equipment, use, height, area, unobstructed maintenance of required yards, and maintenance of buildings or structures within the planning and platting jurisdiction of the city, the following provisions and codes are adopted by reference and incorporated as fully as if set out herein unless otherwise amended by the city:...(14)2020 New Mexico Electrical Code adopted by the state of New Mexico construction industries division (NMAC 14.10.4), as may be amended from time to time, which adopts and amends the National Electrical Code (NEC); and

Full Breakdown

4), which adopts and amends the National Electrical Code (NEC). 1(D). Paragraph B makes noncompliance with any adopted code enforceable under Sections 1-3 and 14-11 SFCC 1987, and paragraph C requires a copy of the adopted codes to be kept on file in the office of building inspections for public review. 00 for panels over 2,000 amps. Temporary power poles, mobile home service and low-voltage work each carry their own listed fee in the same table.

Violations & Fines

Performing electrical work without the permit required under the adopted 2020 NM Electrical Code, or without paying the fees in Table 7-1.11-1, is enforceable under Sections 1-3 and 14-11 SFCC 1987, the penalty sections referenced in Section 7-1.1(B). Building without a permit doubles the original permit fee under the Table 7-1.11-1 administrative fee schedule.

Frequently Asked Questions

What electrical code does Santa Fe use?
The 2020 New Mexico Electrical Code, adopted by reference in Section 7-1.1(A)(14) SFCC 1987. That state code adopts and amends the National Electrical Code, so Santa Fe wiring work is inspected against NEC standards as modified by NMAC 14.10.4.
How much does an electrical permit cost in Santa Fe?
Table 7-1.11-1 sets a $40.00 issuance fee for any commercial or residential electrical permit, then adds panel-specific charges, for example $45.00 for a new residential meter loop up to 100 amps and as much as $900.00 for a commercial panel over 2,000 amps.
What happens if I do electrical work without a permit?
Section 7-1.1(B) makes it enforceable under Sections 1-3 and 14-11 SFCC 1987, and Table 7-1.11-1's administrative fee schedule doubles the original permit fee for work done without one, on top of any other penalty the city imposes.

Sources & Official References

Other rules in Santa Fe

All Santa Fe rules

Compare Santa Fe to another location·View the New Mexico building safety overview

Get notified when Electrical Permits in Santa Fe, NM changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.