Key Facts

Adopted code
California Electrical Code, 2025 Edition
Adopting section
AVMC 13.02.010(C), Ordinance 2025-246
Work before permit
Assessment includes double the required permit fees
Permit fees
Set by City Council resolution
Permit expiration
180 days suspended or abandoned; extensions up to 180 days each
Criminal penalty
Misdemeanor, fine up to $1,000 or six months

Summary

In the City of Aliso Viejo, California, the City Council adopts the California Electrical Code, 2025 Edition, by reference in section 13.02.010(C) of the municipal code. Building Code section 109.4 treats electrical work started before the necessary permits as a violation, and the assessment includes double the required permit fees.

The city council, for the purpose of prescribing regulations for the erecting, construction, enlargement, alteration, repair, improving, removal, conversion, demolition, occupancy, equipment, use, height, area and maintenance of all buildings and structures in the city, hereby adopts the following codes by reference and the amendments to these codes as set forth in this chapter: ... C. The California Electrical Code, 2025 Edition, as published by the National Fire Protection Association; ... 109.4. Fees. ... Failure to pay fees and obtain a permit before commencing work shall be deemed a violation of this chapter. A violation may result in an assessment, which includes double the required permit fees for work on a building, structure, mechanical, gas, electrical or plumbing system before obtaining the necessary permits. Payment of assessed fees shall not relieve any person from fully complying with the requirements of this chapter nor from any other penalties prescribed herein.

Full Breakdown

The City of Aliso Viejo adopts its electrical standard in section 13.02.010(C) of the Aliso Viejo Municipal Code: the California Electrical Code, 2025 Edition, as published by the National Fire Protection Association. The City Council adopted it by Ordinance 2025-246 together with the Building, Residential, Mechanical, Plumbing, Green Building, Energy, Fire and other 2025 codes, and the section declares that these codes, as amended by Chapters 13.02 and 13.04, constitute the building regulations of the city. The adopted codes are on file for public examination in the office of the building official. The amendment sections in Chapter 13.02 are titled for the Building Code, the Residential Code and the Wildland-Urban Interface Code, not the Electrical Code, so the permit and administrative rules come from Chapter 1 of the California Building Code as amended in section 13.02.060.

The permit rule is in section 109.4. Failure to pay fees and obtain a permit before commencing work is a violation, and the assessment includes double the required permit fees for work on a building, structure, mechanical, gas, electrical or plumbing system before obtaining the necessary permits. Paying the assessment does not excuse compliance or other penalties. Permit fees are set by resolution of the City Council under section 13.02.040.

Under section 105.5, every permit issued becomes invalid unless the authorized work commences 12 months after issuance, or if work is suspended or abandoned for 180 days after it starts. The Building Official can grant, in writing, one or more extensions of not more than 180 days each, on a written request that shows justifiable cause. Disputes over alternate materials and methods go to the board of appeals under section 13.02.030, made up of the mayor and the other four council members, with the building official as secretary.

Violations & Fines

Section 13.02.020 makes it unlawful to erect, alter, repair, equip, use or maintain any building or structure contrary to the chapter. A violator is guilty of a misdemeanor, each day is a separate offense, and conviction carries a fine of not more than $1,000, imprisonment of not more than six months, or both. Starting electrical work before the permit also triggers the section 109.4 assessment of double the required permit fees.

Frequently Asked Questions

Which electrical code applies in Aliso Viejo?
The California Electrical Code, 2025 Edition, as published by the National Fire Protection Association, adopted by reference in section 13.02.010(C). The City Council adopted it by Ordinance 2025-246, and the codes as adopted and amended are on file for public examination in the office of the building official.
What happens if I start electrical work before getting a permit?
Section 109.4 treats failing to obtain a permit before commencing work as a violation. The assessment includes double the required permit fees for work on a building, structure, mechanical, gas, electrical or plumbing system. Paying it does not relieve you of full compliance or of other penalties in the chapter.
How long does a permit stay valid?
Under section 105.5 a permit becomes invalid if work is suspended or abandoned for 180 days after it begins, and the 12-month start requirement as printed also applies. The Building Official can grant one or more written extensions of not more than 180 days each, after a written request showing justifiable cause.
Who decides appeals on the building codes?
Section 13.02.030 creates a five-member board of appeals made up of the mayor and the other City Council members, with the building official as secretary. Three members make a quorum, the mayor presides, and the board issues its decisions in writing to the building official with a copy to the appellant.

Sources & Official References

Other rules in Aliso Viejo

All Aliso Viejo rules

California rules heatmap·Compare Aliso Viejo to another location·View the California building safety overview

Get notified when Electrical Permits in Aliso Viejo, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Nearby Cities

How other cities in Orange County handle electrical permits.

Anaheim, CA
Some Restrictions
Costa Mesa, CA
Some Restrictions
Fullerton, CA
Some Restrictions
Garden Grove, CA
Some Restrictions
Huntington Beach, CA
Some Restrictions
Irvine, CA
Some Restrictions
Mission Viejo, CA
Some Restrictions
Newport Beach, CA
Some Restrictions