Aliso Viejo, CA Building Safety: Plumbing Permits (2026)
Key Facts
- Adopted code
- California Plumbing Code, 2025 Edition
- Adopting section
- AVMC 13.02.010(E), Ordinance 2025-246
- Work before permit
- Assessment includes double the required permit fees
- Tankless water heater plans
- Three sets, with water lines, gas lines and venting
- Expedited program fee waiver
- 25 percent of building permit fees under AVMC 15.68.070
- Criminal penalty
- Misdemeanor, fine up to $1,000 or six months
Summary
In the City of Aliso Viejo, California, the City Council adopts the California Plumbing Code, 2025 Edition, in section 13.02.010(E) of the municipal code. Building Code section 109.4 makes plumbing work started before the necessary permits a violation, and the assessment includes double the required permit fees.
The city council, for the purpose of prescribing regulations for the erecting, construction, enlargement, alteration, repair, improving, removal, conversion, demolition, occupancy, equipment, use, height, area and maintenance of all buildings and structures in the city, hereby adopts the following codes by reference and the amendments to these codes as set forth in this chapter: ... E. The California Plumbing Code, 2025 Edition, as published by the International Association of Plumbing and Mechanical Officials; ... 109.4. Fees. ... Failure to pay fees and obtain a permit before commencing work shall be deemed a violation of this chapter. A violation may result in an assessment, which includes double the required permit fees for work on a building, structure, mechanical, gas, electrical or plumbing system before obtaining the necessary permits. Payment of assessed fees shall not relieve any person from fully complying with the requirements of this chapter nor from any other penalties prescribed herein.
Full Breakdown
Section 13.02.010(E) of the Aliso Viejo Municipal Code adopts the California Plumbing Code, 2025 Edition, as published by the International Association of Plumbing and Mechanical Officials. The Mechanical Code is a separate adoption in subsection (D). The City Council adopted both by Ordinance 2025-246 and declared that the codes, as amended by Chapters 13.02 and 13.04, constitute the building regulations of the City of Aliso Viejo, kept on file for public examination in the office of the building official. The amendment sections in Chapter 13.02 are titled for the Building Code, the Residential Code and the Wildland-Urban Interface Code, not the Plumbing Code.
The permit rule sits in section 109.4. Failure to pay fees and obtain a permit before commencing work is a violation, and the assessment includes double the required permit fees for work on a building, structure, mechanical, gas, electrical or plumbing system before obtaining the necessary permits. Fees are set by resolution of the City Council under section 13.02.040, and a permit becomes invalid after 180 days of suspension or abandonment under section 105.5.
Chapter 15.68 adds plumbing-related submittal detail for the city's expedited program. A solar thermal permit request needs three sets of plans that include manufacturer and plumbing details. A tankless water heater request needs three sets of plans with California Energy Code compliance forms, showing a site plan, water lines, gas lines (size and length), venting and electrical. Tankless water heaters and solar thermal systems that meet 50 percent of domestic hot water needs qualify under section 15.68.030(A) for expedited processing, and section 15.68.070 waives 25 percent of the building permit fees when the threshold is met. If the information is complete and approved within the public counter hours, the permit issues the day it is approved.
Violations & Fines
Section 13.02.020 makes it unlawful to erect, alter, repair, equip, use or maintain any building or structure contrary to the chapter. A violator is guilty of a misdemeanor, each day is a separate offense, and conviction carries a fine of not more than $1,000, imprisonment of not more than six months, or both. Plumbing work begun before the permit also draws the section 109.4 assessment of double the required permit fees.
Frequently Asked Questions
Which plumbing code applies in Aliso Viejo?
Do I need a permit before starting plumbing work?
What plans does a tankless water heater permit need?
What is the penalty for plumbing work without a permit?
Sources & Official References
Other rules in Aliso Viejo
California rules heatmap·Compare Aliso Viejo to another location·View the California building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Plumbing Permits in Nearby Cities
How other cities in Orange County handle plumbing permits.