Cheyenne, WY Building Safety: Electrical Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Electrical code
NEC 2023 Edition adopted
Enforcing agency
Building Safety Department
Early-start penalty
Investigation fee = permit fee
Permit fee basis
Project valuation, § 15.08.030

Summary

Cheyenne enforces the 2023 National Electrical Code and requires a permit from the building safety department before any electrical work begins, with a penalty fee for starting early.

Work commencing before permit issuance. Any person who commences any work on a building, structure, electrical, gas, mechanical or plumbing system before obtaining the necessary permits shall be subject to an investigation fee. The investigation fee shall be in an amount equal to the permit fee.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 73).

Full Breakdown

The city adopted the National Electrical Code, 2023 Edition, in Chapter 15.20 of the Cheyenne City Code, amended locally so a service disconnect must sit immediately behind or adjacent to the metering equipment. Separately, the code's permit-administration amendments (Section 15.10.020(H), amending IRC Section R108.6) make clear that electrical work is one of the systems covered by the city's permit-before-work rule: starting the job before the permit is issued triggers an investigation fee equal to the permit fee itself, on top of the standard permit fee set by the valuation-based schedule in Section 15.08.030.

Violations & Fines

Starting electrical work before a permit issues draws an investigation fee equal to the full permit fee; unpermitted work can also be red-tagged and held up pending inspection.

Frequently Asked Questions

Do I need a permit for electrical work in Cheyenne?
Yes. The chief building official's office requires a permit, and starting work first triggers an added investigation fee equal to the permit fee.
What electrical code does Cheyenne use?
The 2023 National Electrical Code, adopted in Chapter 15.20, with a local amendment on service disconnect placement near the meter.

Sources & Official References

Other rules in Cheyenne

All Cheyenne rules

Compare Cheyenne to another location·View the Wyoming building safety overview

Get notified when Electrical Permits in Cheyenne, WY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.