Georgetown, KY Building Safety: Electrical Permits (2026)
Key Facts
- Adopted code
- National Electrical Code, 2014 edition (NFPA 70)
- Permit from
- The building official, under Section 8-2(a)
- Notice to building official
- Before work starts and when ready for inspection
- Before current is furnished
- Electrical inspector's certificate of approval
- Correction period for existing violations
- 30 days before service can be disconnected
- Inspections performed by
- State-certified electrical inspectors
Summary
Georgetown adopts the National Electrical Code, 2014 edition (NFPA 70), by reference. Electrical work needs a permit from the building official under Section 8-2, the installer must notify the building official before starting and when the work is ready for inspection, and no one can furnish current until the electrical inspector approves the installation and issues a certificate of approval.
The National Electrical Code, 2014 edition, also known as the NFPA 70, is hereby adopted by reference as if copied in full and set forth herein. ... It shall be the duty of the person installing electrical wiring or equipment, or repairing or rearranging same, to notify the building official prior to the time the work is commenced, and also when the work is ready for inspection, and it shall be unlawful for any person to conceal any such electrical wiring or installations until after same has been reported to the building official, and has been inspected and approved by the building official. ... It shall be unlawful for any person, including any electric light or power company, to connect with or furnish current to any electrical installation within the corporate limits of the city until after such electrical installation shall have been inspected and approved by the electrical inspector, and a certificate of approval issued by him.
Official source re-checked November 3, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 4).
Full Breakdown
Section 8-57 adopts the National Electrical Code, 2014 edition, also known as NFPA 70, by reference as if copied in full and set forth in the Code. Section 8-58 sets the working standard: all electrical wiring in the city, when installed to be connected to a source of electrical energy, must be sufficiently insulated, supported and protected to be reasonably free from hazards to life and property caused by over-loading, short-circuiting and improper protection or installation of electrical equipment, and must comply fully with the National Electrical Code and the National Electrical Safety Code.
The permit requirement sits in Section 8-2(a), which requires any owner, authorized agent or contractor who desires to insert items such as heating, electrical, etc., to apply to the building official first and obtain the required permit. Fees follow the schedule kept by the city clerk under Section 8-34. Section 8-32 says all electrical inspections are performed by persons certified by the state department of housing, buildings and construction as an electrical inspector, and Section 8-59 authorizes the council to contract with private electrical inspection firms.
Inspection timing is fixed by Section 8-60. The person installing, repairing or rearranging wiring or equipment must notify the building official before the work is commenced and again when it is ready for inspection, and no one can conceal wiring until it has been reported, inspected and approved. Under Section 8-61, nobody, including an electric light or power company, can connect with or furnish current to an installation until the electrical inspector has approved it and issued a certificate of approval.
For existing wiring, Section 8-63 has the electrical inspector inspect on complaint by an occupant or request by an owner. On finding a violation that creates a threat of bodily injury or property damage, the inspector gives the owner 30 days to correct it, provides reasonable assistance, and if there is no substantial progress at the end of 30 days can cause service to be disconnected without further notice. For an imminent threat of serious bodily injury or substantial property damage, the 30-day period can be waived. The fire chief or a designee can cut off electrical currents in emergencies.
Violations & Fines
Failure to comply with the wiring standard is prima facie evidence of a violation of the electrical article under Section 8-58(b). Concealing wiring before inspection and approval violates Section 8-60, and connecting current before the certificate of approval violates Section 8-61. The inspector can disconnect service under Section 8-63 when a threat is not corrected, and Section 2-843 lets a code enforcement officer order work stopped. Section 2-842 caps civil fines for provisions the Code Enforcement Board enforces at $2,000.00 contested and $1,000.00 uncontested.
Frequently Asked Questions
Which electrical code does Georgetown enforce?
Do I need a permit for electrical work in Georgetown?
When does the power company get to turn the power on?
What happens if my existing wiring is found unsafe?
Sources & Official References
Other rules in Georgetown
Compare Georgetown to another location·View the Kentucky building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.