Key Facts

Adopted code
Georgia Minimum Standard Electrical Code (NEC)
Governing sections
§§ 14-36, 14-53(c), 14-91
Permit issued by
Houston County Building Official
Application lapse
Abandoned after 6 months without permit
Extension available
Up to 90 days, written request required
Violation
Misdemeanor; each day is separate offense (§14-61)

Summary

Any electrical installation, alteration, repair or replacement in unincorporated Houston County falls under the electrical code adopted in Chapter 14 of the county's Code of Ordinances: Georgia's Minimum Standard Electrical Code, which is the National Electrical Code (NEC) with Georgia amendments. Sec. 14-91 requires the owner, agent or contractor to apply to the building official and obtain a permit before starting the work.

These county ordinances apply to unincorporated areas of Houston County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Electrical. The provisions of the International Electrical Code with Georgia Amendments shall apply to the installation of electrical systems, including alterations, repairs, replacement, equipment, appliances, fixtures, fittings and appurtenances thereto.

Full Breakdown

Sec. 14-36 of the Houston County, Georgia General Code adopts the "Georgia State Minimum Standard Electrical Code (National Electrical Code with Georgia State Amendments)" by reference for unincorporated Houston County, one of eight technical codes the article incorporates alongside the building, residential, fire, plumbing, mechanical, gas and energy codes. Sec. " Before any of that work starts, Sec. 14-91(a) requires the owner, authorized agent or contractor to "first make application to the building official and obtain the required permit for the work" whenever the installation is regulated by the technical codes.

An application filed under Sec. 14-91(d) must be made on the county's form, describe the proposed work and its location, and be signed by the owner or an authorized agent. Under Sec. 14-91(e), that application lapses if a permit is not issued within six months of filing, though the building official can grant one or more 90-day extensions on a written, justified request. The building official also holds inspection authority under Sec. 14-72, entering a building or premises at reasonable times to check for unsafe electrical conditions, and stop-work power under Sec. 14-73 if work proceeds without the required permit.

Violations & Fines

Performing electrical work without the Sec. 14-91 permit, or installing wiring that departs from the plans the building official approved, is a misdemeanor under Sec. 14-61's "Violations and penalties" clause. Each day the unpermitted or noncompliant work continues counts as a separate offense, and a conviction is punished "within the limits and as provided by state laws," the standard county ordinance ceiling the Code cross-references.

Frequently Asked Questions

Does Houston County require a permit for electrical work?
Yes. Sec. 14-91(a) requires any owner, agent or contractor doing electrical installation, alteration, repair or replacement work regulated by the technical codes to first apply to the building official and obtain a permit. The work itself must follow the Georgia State Minimum Standard Electrical Code, the NEC with Georgia amendments, adopted for the county by Sec. 14-36.
What electrical code does Houston County, Georgia use?
The county has adopted the Georgia State Minimum Standard Electrical Code, which Sec. 14-36 defines as the National Electrical Code with Georgia State Amendments. Sec. 14-53(c) applies that code to "the installation of electrical systems, including alterations, repairs, replacement, equipment, appliances, fixtures, fittings and appurtenances thereto" throughout unincorporated Houston County.
How long is an electrical permit application good for before it expires?
Sec. 14-91(e) treats an application as abandoned six months after filing if no permit has been issued by then. The building official can grant one or more extensions of up to 90 days each, but only if the applicant requests the extension in writing and shows a justifiable cause for the delay.

Sources & Official References

Other rules in Houston County

All Houston County rules

Compare Houston County to another location·View the Georgia building safety overview

Get notified when Electrical Permits in Houston County, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.