Key Facts

Electrical code adopted
2022 CA Electrical Code (§15.16.010)
Residential reconnection trigger
1 year disconnected
Commercial/industrial trigger
180 days disconnected
Engineer-stamped plans required
Over 400A/600V or 15,000 sq ft
New service limit
Load allowed by zoning

Summary

Fresno County adopts the 2022 California Electrical Code as its wiring standard under Code Section 15.16.010, and layers on local permit triggers, including a required inspection permit before reconnecting long-disconnected service. New electrical service is also capped to whatever load or use the property's zoning actually allows.

City-specific rules exist: Fresno, and Clovis have their own electrical permits rules that differ from Fresno County's county-level regulations. If you live in one of those cities, check the city-specific page instead.

2.For all existing residential buildings and agricultural service poles where service has been disconnected for one (1) year or more, the service may not be reconnected without inspection and approval from the Building Official. A permit is required for the inspection.E.Article 230.2, Number of Services, is amended by adding Special Condition No. 7 to read as follows: Special Condition No. 7: For tenant spaces when one (1) occupant expands operations into an adjacent tenant space and demising walls are removed or openings in such walls are created, wiring systems for each service shall be completely segregated from the wiring systems of other services and shall not cross over a defined demarcation line which shall be described at each service.

F.Permits for new electrical service installations will be limited to installations that serve a connected load or approved use as allowed by the property's zoning.G.Approved temporary electrical service installations shall comply with section 15.04.090.C of this chapter.H.Reserved. (Ord. No. 23-001, § 1(Exh. 2), 2-28-2023; Ord. No. 19-025, § 1(Exh. B), 12-10-2019; Ord. No. 13-024, § 1(Exh. B), 11-12-2013; Ord. No. 11-005, § 1, 5-24-2011; Ord. 07-049, Exh. A)

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 51).

Full Breakdown

010 adopts "the 2022 Edition of the California Electrical Code, including Informative Annex A through Informative Annex G" as the wiring standard for the unincorporated county, enforced by the Building Official within the Department of Public Works and Planning. 020 amends several parts of that code for local conditions. " The same subsection imposes a shorter, 180-day trigger for commercial and industrial buildings and places of assembly, also requiring an inspection permit before reconnection, with approval withheld if any unsafe wiring or equipment is found.

Subsection (F) ties new electrical service directly to land use: "Permits for new electrical service installations will be limited to installations that serve a connected load or approved use as allowed by the property's zoning," so a service upgrade can be denied if it would support a use the parcel isn't zoned for. 020(C) requires that services over 400 amps or 600 volts, or buildings over 15,000 square feet, have their electrical plans prepared by a California-licensed electrical engineer. 030: any new electrical work performed as part of a building addition or alteration must comply fully with the adopted Electrical Code, and the Building Official decides how much of the untouched existing wiring can remain without being brought up to current standards.

060 requires all unused wiring to be pulled out of a structure and calls for a rough electrical inspection once conductors and cable are protected from weather and physical damage.

Violations & Fines

Reconnecting electrical service to a residential building after a year-long disconnection, or a commercial building after 180 days, without first obtaining the required inspection permit violates Section 15.16.020(D). Because Chapter 15.16 sets no separate penalty of its own, a violation falls back to the county's general misdemeanor penalty under Section 1.12.010: up to a $500 fine, up to six months in jail, or both, and the Building Official can also order the serving utility to disconnect power from a noncompliant installation.

Frequently Asked Questions

Do I need a permit to turn electrical service back on after it's been off a while?
Yes, in some cases. Under Section 15.16.020(D), a residential building or agricultural service pole disconnected for a year or more, or a commercial/industrial building or assembly space disconnected for 180 days or more, needs a Building Official inspection and permit before reconnection.
Can I get a bigger electrical service than my property's zoning allows?
No. Section 15.16.020(F) says permits for new electrical service installations "will be limited to installations that serve a connected load or approved use as allowed by the property's zoning," so the service size is capped by what the parcel's zoning permits.
When do I need a licensed electrical engineer to prepare my plans?
Section 15.16.020(C) requires plans stamped by a California-licensed electrical engineer whenever the service exceeds 400 amperes or 600 volts, or the building is larger than 15,000 square feet, with a narrow exception under Business and Professions Code Section 6737.3.

Sources & Official References

Other rules in Fresno County

All Fresno County rules

California rules heatmap·Compare Fresno County to another location·View the California building safety overview

Get notified when Electrical Permits in Fresno County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Cities Across Fresno County