Fresno, CA Building Safety: Electrical Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Adopted code
2025 California Electrical Code (2023 NEC base)
Administered under
FMC Ch. 11, Art. 1 + CEC Art. 89
Local name
"Fresno Electrical Code"
Conflicts resolved by
Fresno Building Code controls
Effective
Ordinance 2025-040, eff. 10-31-25
Violations
misdemeanor under § 114.4.1

Summary

Fresno enforces electrical work under the 2025 California Electrical Code, which itself incorporates the 2023 National Electrical Code with state amendments. Municipal Code § 11-104 adopts it by reference as the 'Fresno Electrical Code,' administered by the same Building Official who runs the rest of the building code.

The California Electrical Code, 2025 Edition, which may be referred to in the Code as the CEC, as promulgated by the California Building Standards Commission, which incorporates the adoption of the 2023 Edition of the National Electrical Code as amended with necessary California amendments and the 2023 National Electrical Code of the National Fire Protection Association, is hereby adopted by the City of Fresno and incorporated by reference into the Fresno Building Code, except that Chapter 1 of the Fresno Building Code in addition to Article 89 of the California Electrical Code shall apply to the administration of the CEC. The CEC, incorporated into the Fresno Building Code, shall be referred to as the Fresno Electrical Code. For purposes of administering the Fresno Electrical Code, all references in Chapter 1 of the Fresno Building Code to the "building code" or "code" shall mean and include the Fresno Electrical Code. Where provisions of Chapter 1 of the Fresno Building Code overlap with provisions of Article 89 of the Fresno Electrical Code, the Fresno Building Code shall control.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 54).

Full Breakdown

Fresno Municipal Code § 11-104 adopts the 2025 California Electrical Code, built on the 2023 National Electrical Code of the National Fire Protection Association with California-specific amendments, by reference into the Fresno Building Code, and directs that Chapter 1 of the Fresno Building Code plus Article 89 of the CEC govern how it's administered. Once adopted, the CEC is called the 'Fresno Electrical Code,' and every reference in Chapter 1 of the Fresno Building Code to the 'building code' is read to include it. Where Chapter 1 of the Fresno Building Code and Article 89 of the Fresno Electrical Code overlap, the Fresno Building Code controls.

A copy of the CEC is kept on file for public inspection at the Planning and Development Department, Building and Safety Services Division. 1's requirement that the electrical meter be installed and operational before final electrical inspection applies directly to electrical permits. These provisions took effect under Ordinance 2025-040 on October 31, 2025, replacing Fresno's prior electrical-code adoption.

Violations & Fines

Doing electrical work that doesn't comply with the adopted California Electrical Code, or without the required Fresno electrical permit, is a code violation: § 114.4.1 of the Fresno Building Code makes any violation of the code a misdemeanor. Orders or interpretations by the Building Official regarding electrical work can be appealed to the Building Standards Appeals Board under § 113.

Frequently Asked Questions

What electrical code does Fresno enforce?
The 2025 California Electrical Code, built on the 2023 National Electrical Code with state amendments. Fresno Municipal Code § 11-104 adopts it by reference and calls it the 'Fresno Electrical Code,' administered under Chapter 1 of the Fresno Building Code together with Article 89 of the CEC.
Who administers electrical permits in Fresno?
The Building Official, the Planning and Development Department Director or a designee under FMC § 11-102 [104.1], administers the Fresno Electrical Code the same way as the rest of the Fresno Building Code, and where the two overlap, the Fresno Building Code's Chapter 1 provisions control.
What happens if electrical work doesn't meet Fresno's adopted code?
It's a misdemeanor under § 114.4.1 of the Fresno Building Code, which applies to any violation of the adopted California Electrical Code. If you disagree with a Building Official order or interpretation on electrical work, you can appeal to the Building Standards Appeals Board under § 113.

Sources & Official References

Other rules in Fresno

All Fresno rules

California rules heatmap·Compare Fresno to another location·View the California building safety overview

Get notified when Electrical Permits in Fresno, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.