Portsmouth, VA Building Safety: Electrical Permits (2026)
Key Facts
- Governing section
- City Code § 7-133
- Fee basis
- Priced per 50 amperes of service
- Three-phase break point
- Rate changes after first 1,000 amperes
- Temporary power
- Separate 60A/100A/construction tiers
- Enforcement
- § 7-102 misdemeanor for unpermitted work
Summary
Electrical work in Portsmouth needs its own permit and inspection under City Code § 7-133, with fees scaled by amperage: a flat minimum permit charge, per-50-ampere increments for new or changed single- and three-phase services, and separate line items for temporary construction power and pool equipment.
(a)The fees for electrical permits shall be as set forth in appendix A to this Code for the following categories:(1)Minimum permit fee.(2)a.Temporary service, 60 amperes.b.Temporary service, 100 amperes.c.Temporary service for construction regardless of amperage.(3)a.Fees for new services whether single- or three-phase include all circuits, motors, generators and other derivations of an electrical system. Single-phase per 50 amperes.b.Three-phase service per 50 amperes for first 1,000 amperes and an additional amount per 50 amperes for remaining amperes after 1,000. ... (b)The fees referred to in this section shall be charged based upon amperage for each piece of electrical apparatus inspected and not on the aggregate number of amperes.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 65).
Full Breakdown
Section 7-133 sets out the electrical permit fee structure administered by the department of permits and inspections. Beyond a flat minimum permit fee, the schedule charges by increments of 50 amperes for new single-phase or three-phase electrical services, with three-phase service billed per 50 amperes up to the first 1,000 amperes and at a different rate for amperage beyond that threshold. Temporary service connections get their own tier, split between 60-ampere and 100-ampere temporary hookups and a separate rate for temporary construction power regardless of amperage.
Changing an existing service is billed the same way as a new service, per 50 amperes, with any additional circuits added during the change billed under the separate additions-and-repairs schedule, which covers each piece of equipment connected and each circuit or feeder installed, extended, relocated or repaired. Pool wiring gets two dedicated line items, pool inspection and pool grounding, plus a fee for inspecting a temporary release. All of these amperage-based fees, per subsection (b), are charged per piece of electrical apparatus inspected rather than added up across a building's total amperage.
Failing to pull this permit before starting electrical work is enforced the same way as any other trade permit: § 7-102 makes commencing electrical work before obtaining the necessary permit a misdemeanor.
Violations & Fines
Starting electrical work, including new services, changes of service or circuit additions, before obtaining the permit required by § 7-133 is a misdemeanor under § 7-102, on top of the permit and plan-review fees the electrician or owner still owes once the work is caught.
Frequently Asked Questions
Do I need a separate permit for electrical work in Portsmouth?
How does Portsmouth price an electrical permit?
Is there an extra fee for pool electrical work?
Sources & Official References
Other rules in Portsmouth
Compare Portsmouth to another location·View the Virginia building safety overview