Key Facts
- Governing section
- City Code § 7-101
- Inspector
- Dept. of Permits and Inspections or designee
- Extra inspections
- Ordered for scope or complexity
- Reinspection fee
- Set in appendix A, paid up front
- Elevator exception
- § 7-136 replaces standard reinspection fee
Summary
Every stage of permitted construction in Portsmouth has to pass inspection by the department of permits and inspections, or a building-official-designated third party, before work is deemed complete. City Code § 7-101 lets inspectors demand extra visits and charges a reinspection fee for each recheck.
The inspections required under the provisions of the building code shall be performed by an inspector from the department of permits and inspections, or by a third party designated by the building official upon notification from the permit holder or such holder's agent. Such inspector shall either approve that portion of the work as completed or shall notify the permit holder or his agent where such work fails to comply with the building code or departmental regulation. Additional inspections may be required by the inspector where, in the inspector's judgment, such inspections are necessary because of the scope or complexity of the work to be installed or performed. Except as provided in section 7-136, a reinspection fee as set forth in appendix A to this Code shall be paid prior to each reinspection unless waived by the building official.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 65).
Full Breakdown
Section 7-101 puts inspection authority in the hands of an inspector from the department of permits and inspections, though the building official may designate a third party to perform the inspection instead, triggered once the permit holder or an agent requests it. After each inspection the inspector either signs off on the portion of work completed or notifies the permit holder where the work fails to meet the building code or departmental regulation, so a single inspection can end in approval or a formal notice of noncompliance.
The inspector is not limited to the standard visits: additional inspections can be ordered whenever the scope or complexity of the installed or performed work makes that judgment necessary, meaning larger or more technical jobs can expect more inspection stops than a routine remodel. Every reinspection carries its own fee, set in appendix A to the Code, due before the recheck happens, unless the building official waives it. Elevator work is carved out from that reinspection fee under § 7-136, which bundles a processing fee into its own periodic inspection schedule instead of charging a separate reinspection charge each time.
Violations & Fines
Executing permitted work without calling for and receiving the required inspections, or occupying a building before a certificate of occupancy issues after final inspection, is a misdemeanor under § 7-102, and each unpaid reinspection fee under § 7-101 must still be paid before work can proceed.
Frequently Asked Questions
Who inspects permitted construction work in Portsmouth?
Does Portsmouth charge for reinspections?
Can Portsmouth require more inspections than usual on my project?
Sources & Official References
Other rules in Portsmouth
Compare Portsmouth to another location·View the Virginia building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.