Warrick County, IN Building Safety: Electrical Permits (2026)
Key Facts
- Permit trigger
- Electrical work over $750 (§ 150.15)
- Enforcing office
- Building Commissioner
- Adopted code
- Indiana Electrical Code, Article 17 (675 IAC)
- Application
- Written form under § 150.16
- General fine cap
- Up to $2,500 (§ 150.99(A))
- Notice fines
- $250 / $500 / $750 escalating
Summary
In unincorporated Warrick County, Indiana, any electrical improvement costing more than $750, including a new meter base, panel upgrade, furnace, or hot water heater, needs a building permit from the Building Commissioner before work starts under County Code § 150.15. The county also enforces the Indiana Electrical Code, Article 17 of the state building rules, adopted by reference under § 150.40(A).
A permit shall be required before beginning any new construction of any building or structure or before beginning any structural improvement to any building or structure not hereinafter exempted, the cost of which construction or improvements exceeds $2,500; or is more than 120 square feet; or before beginning construction of any improvement to any building or structure involving modification, changing or new installation of any electrical, plumbing or mechanical improvement, the cost of which exceeds $750, including installation of any furnace, hot water heater, new meter base, meter base relocation, panel upgrade; load control device or before electrical meter is installed following a fire; ... (A) ... Pursuant to I.C. 22-13-2-3(b) , the rules of the Indiana Fire Prevention and Building Safety Commission as set out in the following Articles of Title 675 of the Indiana Administrative Code are hereby incorporated by reference in this code and shall include any later amendments to those rules. ... (4) Article 17 - Indiana Electrical Code
Full Breakdown
The Building Commissioner administers Warrick County's electrical permitting under Chapter 150. Section 150.15 sets the trigger: any modification, change, or new installation of electrical work costing more than $750 requires a permit before construction begins, alongside separate thresholds for general construction ($2,500 or 120 square feet). Covered work explicitly includes furnace installation, water heaters, new meter bases, meter base relocation, panel upgrades, load control devices, and reconnecting an electrical meter after a fire. Applicants file a written application under § 150.16 with contact information, detailed plans, and a scaled plot plan showing the structure relative to property lines, streets, and sidewalks; work needing state Design Release under I.C.
22-15-3 must include that release. Fees follow the schedule the County Building Commission adopted March 19, 2003, effective April 7, 2003 (§ 150.17), payable at the Building Commissioner's office or online through the county's designated vendor, with the vendor's card-processing fees passed to the applicant. On the code side, § 150.40(A) incorporates by reference the rules of the Indiana Fire Prevention and Building Safety Commission under I.C. 22-13-2-3(b), specifically Article 17 of Title 675 of the Indiana Administrative Code, the Indiana Electrical Code, along with the Building, Residential, Plumbing, Mechanical, Energy Conservation, Swimming Pool, and Fire Codes.
Two copies of the adopted rules sit on file with the clerk of the legislative body for public inspection under I.C. 36-1-5-4. The Building Commissioner and the Fire Prevention and Building Safety Commission can grant variances, but a Commissioner-issued variance is not effective until the state commission approves it under I.C. 22-13-2-7(b).
Violations & Fines
Under § 150.99, unpermitted or noncompliant electrical work draws escalating civil fines: $250 for failing to correct a violation within ten days of written notice, an added $500 if not corrected within 20 days, and an added $750 if not corrected within 30 days, on top of a general fine of up to $2,500 under § 150.99(A). The Commissioners or Building Commissioner may also pursue a court order to remove occupants from a noncompliant structure under § 150.99(C).
Frequently Asked Questions
Do I need a permit for electrical work in unincorporated Warrick County?
What electrical code does Warrick County use?
Who issues Warrick County electrical permits?
What happens if I skip the permit?
Sources & Official References
Other rules in Warrick County
Compare Warrick County to another location·View the Indiana building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.