Key Facts

Citation
DuPage County Code § 8-115.2
Advance notice
1 day minimum for each inspection
Inspection hours
8:00 A.M. to 4:00 P.M., workdays
Backfill inspection
Requires a spotted plat of survey first
Occupancy gate
Final inspection before Sec. 8-119.1 certificate
Penalty
$100 to $1,000 per day, Sec. 8-117.4

Summary

DuPage County's Building Code spells out a full sequence of mandatory inspections, from erosion control before excavation through electrical, plumbing, HVAC, radon, framing and a final walkthrough, and requires at least one day's advance notice for each. Skipping a required stage before covering the work forces it back open for inspection.

City-specific rules exist: Naperville has its own building inspections rules that differ from DuPage County's county-level regulations. If you live in Naperville, check the city-specific page instead.

Owner or contractor is required to contact the Building Official at least one day in advance for all required inspections. The following inspections shall be required:a.Erosion Control: Before any excavation occurs and after all required soil erosion control measures have been installed.b.Footing: Before concrete is poured and after footing excavation has been completed and access drive and culvert is installed...i.Framing: Before any insulation, vapor barrier, or wall finish is applied and after the framing fire-stopping is completed...o.Electrical Service: At the time the electrical service is to be energized or re-energized...u.Final Inspection: After all work is completed as proposed on approved plans, Illinois energy requirements, and all other conditions of the permit.3.Inspections shall be arranged on regular workdays between 8:00 A.M. and 4:00 P.M.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 14 Update 1).

Full Breakdown

Sec. 8-115.2, REQUIRED INSPECTIONS, requires the owner or contractor to "contact the Building Official at least one day in advance for all required inspections," then lists them by construction stage: erosion control before excavation, footing before concrete is poured, foundation walls where reinforcement is used, backfill only after a spotted plat of survey showing foundation location and elevation is submitted, pre-pour concrete for flatwork, under-slab plumbing/radon/electrical/insulation before slabs are poured, framing before insulation or wall finish goes up, house wrap before exterior cladding, rough plumbing/electrical/HVAC before insulation, an insulation inspection tied to State of Illinois Energy Efficient Building Code compliance, masonry and prefab fireplace stages, a grading inspection requiring an as-built drawing sealed by a registered land surveyor or Illinois professional engineer, plumbing final, and a final inspection after all work and permit conditions are complete.

Inspections are limited to "regular workdays between 8:00 A.M. and 4:00 P.M.," still with one day's advance call required. If the Building Official arrives and the job isn't ready, Sec. 8-115.2(1) allows a re-inspection fee under the fee schedule, and no further inspections proceed until it's paid. Sec. 8-115.1 also lets the Building Official run a preliminary inspection of the site before ever issuing the permit. A final inspection under Sec. 8-115.3 must happen, and any discrepancies from the approved plans noted, before the county will issue the Certificate of Use and Occupancy required by Sec. 8-119.1 to actually occupy the building.

Violations & Fines

Covering work before its required inspection, or continuing after a failed one, is enforced as an unlawful act under Sec. 8-117.1 and can draw a Notice of Violation under Sec. 8-117.2 with fourteen days to correct or schedule the missed inspection. Continuing fines run $100.00 to $1,000.00 per day under Sec. 8-117.4, and the Building Official can issue a Stop Work Order under Sec. 8-118.1 that carries its own $100.00 to $1,000.00 daily fine for continued work under Sec. 8-118.2.

Frequently Asked Questions

How much notice does DuPage County need before a required building inspection?
At least one day. Sec. 8-115.2 requires the owner or contractor to contact the Building Official at least one day in advance for every required inspection stage.
What inspections does DuPage County require during a home build?
Sec. 8-115.2 lists a full sequence: erosion control, footing, foundation walls, backfill, under-slab plumbing/radon/electrical, framing, house wrap, rough plumbing/electrical/HVAC, insulation, grading, plumbing final, and a final inspection, each tied to a specific construction stage.
Can DuPage County charge me for a missed inspection appointment?
Yes. If the Building Official arrives and the job isn't ready or accessible, Sec. 8-115.2(1) allows a re-inspection fee under the fee schedule, and no further inspections are scheduled until it's paid.

Sources & Official References

Other rules in DuPage County

All DuPage County rules

Compare DuPage County to another location·View the Illinois building safety overview

Get notified when Building Inspections in DuPage County, IL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Cities Across DuPage County