Folsom, CA Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Amendment adds
CBC Section 110.7 Reinspections
Fee set by
City council resolution
Trigger examples
Unready work, missing plans/permit
Payment rule
No further inspection until fee is paid
Violation
Misdemeanor, up to $1,000 / 6 months
Admin sanction
Level E, $100-$10,000

Summary

Folsom charges a reinspection fee any time a building inspector shows up and the work is not ready, prior correction notices are unresolved, or the permit and approved plans are not on site. Municipal Code Section 14.02.050(K) adds Section 110.7 Reinspections to the adopted California Building Code, and no further inspection proceeds until the fee is paid.

K. Section 110 Inspections—Add additional section to read as follows: Section 110.7 Reinspections is added as follows: 110.7 Reinspections. A reinspection fee may be assessed for each inspection or reinspection when any of the following conditions exist: 1. Such portion of work for which inspection is called is not completely ready. 2. Previous written or verbal correction notices have not been complied with. 3. The job address is not clearly posted and clearly visible from the street or the front of the building. 4. The inspector has no access to the work to be inspected. 5. The approved plans are not readily available to the inspector. 6. The building permit, application, appropriate documents, or any previous correction notice(s) are not available at the job site. 7. Deviating from the approved plans requiring further approval of the Building Official. ... To obtain a reinspection, the applicant, or his/her designee, shall first pay the reinspection fee in accordance with resolution adopted by the City Council. In instances where reinspection fees have been assessed, no additional inspection of the work will be performed until the reinspection fees have been paid.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 1369, passed April 28, 2026).

Full Breakdown

050. 7, Reinspections, listing seven conditions that can trigger a reinspection fee: the work called for inspection is not completely ready, prior written or verbal correction notices were not addressed, the job address is not clearly posted and visible from the street, the inspector cannot access the work, the approved plans are not available on site, the permit or prior correction notices are not at the job site, or the contractor deviates from approved plans in a way that needs further Building Official approval. The ordinance says it is not meant to charge a fee the first time an inspection fails purely for a code compliance issue; it targets the practice of calling for inspections before a project is actually ready or accessible.

The reinspection fee is set by city council resolution, and the applicant or their designee must pay it before requesting a new inspection; once assessed, no further inspection of the work is performed until the fee is paid. 1, amended under subsection L, bars occupying or changing the use of a building until the Building Official issues a certificate of occupancy, and subsection M lets the Building Official grant a Temporary Certificate of Occupancy only after utility clearance and payment for remaining inspections.

Violations & Fines

Occupying a building before the certificate of occupancy is issued, or without paying an assessed reinspection fee, is enforced under Section 14.02.070: a violation of Title 14 is both a misdemeanor, punishable by up to a $1,000 fine or six months in county jail, and a Level E administrative violation carrying a separate $100 to $10,000 sanction under Section 1.09.012.

Frequently Asked Questions

When does Folsom charge a reinspection fee?
Under Section 14.02.050(K), adding CBC Section 110.7, a fee applies when the work is not ready, earlier correction notices were ignored, the job address is not visible, the inspector cannot access the site, or the approved plans and permit are not available on site.
Is the first failed inspection billed?
No. Section 110.7 says it is not meant to charge a fee the first time an inspection fails purely for a code-compliance issue; it targets the practice of scheduling inspections before the project or site is actually ready, or when plans and permit documents are missing at the site.
Can I get a temporary certificate of occupancy?
Yes. Under Section 14.02.050(M), temporary occupancy requires applying for a Temporary Certificate of Occupancy, getting clearance to connect gas and electric utilities, and paying for the remaining inspections needed to reach final approval for full occupancy.
What's the penalty for occupying without a certificate of occupancy?
Section 14.02.070 makes any Title 14 violation, including unauthorized occupancy under Section 111.1, a misdemeanor punishable by up to a $1,000 fine or six months in jail, plus a Level E administrative sanction of $100 to $10,000 under Section 1.09.012.

Sources & Official References

Other rules in Folsom

All Folsom rules

California rules heatmap·Compare Folsom to another location·View the California building safety overview

Get notified when Building Inspections in Folsom, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.