Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
Franklin Municipal Code § 12-105
Required before
Occupying new, altered, or reclassified buildings
Prerequisite inspections
Building, zoning, fire, streets, stormwater, landscaping
Temporary certificate term
Up to 30 days, renewable
Penalty
Misdemeanor fine per Appendix A (§ 12-105(7))

Summary

Franklin, Tennessee requires a certificate of use and occupancy before anyone occupies a building, structure, or parcel that was constructed, expanded, renovated, or has a change of use. Franklin Municipal Code § 12-105 conditions that certificate on passing every required building, zoning, fire, streets, stormwater, and landscaping inspection, and the Building and Neighborhood Services Department can issue a 30-day temporary certificate for projects that aren't fully finished.

(1)Certificate of use and occupancy required. It shall be unlawful for any person to occupy or use a building or structure, part of a building or structure, or parcel of land prior to the issuance of a certificate of use and occupancy. The issuance of a certificate of use and occupancy shall be a prerequisite to the occupation, reoccupation, or use of a building, structure, or parcel of land when:(a)A building or structure has been constructed.(b)A building, structure, or portion thereof has been subject to an expansion, addition, renovation, and/or reconstruction.(c)A building, structure, or parcel of land has a change in its occupancy, use, and/or occupant....(3)Issuing certificates of use and occupancy. A certificate of use and occupancy shall not be issued until all required building, zoning, fire, streets, water management, stormwater, landscaping, green infrastructure, and other related building and site improvement inspections have been performed and approved in their entirety.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 30 Update 1).

Full Breakdown

' Applicants file with the building official concurrent with the building permit application, or before a change of use if no permit is required. Before the certificate issues, subsection (3) requires that 'all required building, zoning, fire, streets, water management, stormwater, landscaping, green infrastructure, and other related building and site improvement inspections have been performed and approved in their entirety,' and any performance sureties tied to the project must be transferred to maintenance obligations. The final certificate must include everything required by Section 111 of the International Building Code plus the zoning uses on the site and any special conditions from the approved development or site plan.

For projects not yet fully finished, subsection (4) lets the building official issue a temporary certificate for any portion 'which may be safely occupied prior to the final completion,' good for up to 30 days and renewable in 30-day increments upon a new application and fee. Subsection (5) adds a separate certificate of completion for phased, multi-tenant developments, confirming the building and site improvements are functional even though it does not itself authorize occupancy; a temporary certificate of completion under subsection (6) follows the same 30-day renewal structure.

Violations & Fines

Occupying a building before the certificate issues, or after a temporary certificate has expired or been revoked, is a misdemeanor under § 12-105(7), punishable by the fine set in Appendix A, Comprehensive Fees and Penalties; application fees for every temporary and final certificate of use and occupancy or completion are likewise fixed in Appendix A under § 12-105(8).

Frequently Asked Questions

Can I move into a new building in Franklin before final inspections are done?
No. Section 12-105 makes it unlawful to occupy a building, structure, or parcel before a certificate of use and occupancy issues, and that certificate requires every applicable building, zoning, fire, streets, stormwater, and landscaping inspection to be performed and approved first.
What if my Franklin project isn't fully finished but I need to move in?
Section 12-105(4) lets the building official issue a temporary certificate of use and occupancy for any portion of the project that can be safely occupied, valid for up to 30 days and renewable with a new application and fee if work isn't complete by the deadline.
What happens if I occupy a Franklin building without the required certificate?
It's a misdemeanor under § 12-105(7), punishable by the fine listed in Appendix A of the Comprehensive Fees and Penalties schedule, and it applies whether the certificate was never issued or a temporary certificate has expired or been revoked.

Sources & Official References

Other rules in Franklin

All Franklin rules

Compare Franklin to another location·View the Tennessee building safety overview

Get notified when Building Inspections in Franklin, TN changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.