Alachua County, FL Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Governing section
§ 331.03, FBC § 110.3
Building sequence
Foundation, framing, sheathing, wall covering, roofing, final
Pool inspections
Excavation/rebar stage, then final enclosure check
Duty to request
Permit holder must notify official (§ 110.5)
Enforcing agency
Alachua County Growth Management Building Division
Penalty
Misdemeanor, separate offense per day

Summary

Alachua County requires a sequence of building-official inspections before permitted work can be occupied, under County Code § 331.03 (Florida Building Code § 110.3). Foundation, framing, sheathing, exterior wall covering, roofing and final inspections are mandatory for buildings, with separate stages for swimming pools, demolition and manufactured buildings. The building official sets the timing and elements checked at each stage.

These county ordinances apply to unincorporated areas of Alachua County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

110.3 Required inspections. The building official upon notification from the permit holder or his or her agent shall make the following inspections and shall either release that portion of the construction or shall notify the permit holder or his or her agent of any violations which must be corrected in order to comply with the technical codes. The building official shall determine the timing and sequencing of when inspections occur and what elements are inspected at each inspection.

Building

1.Foundation inspection. To be made after trenches are excavatedand forms erected, and shall at a minimum include the following building components:•Stem-wall•Monolithic slab-on-grade•Piling/pile caps•Footers/grade beams...6.Final inspection. To be made after the building is completed and ready for occupancy.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 63).

Full Breakdown

3 of Alachua County's locally amended Building Code (Chapter 331) lists the inspections the building official must perform once notified by the permit holder or an authorized agent. For ordinary construction the sequence runs: a foundation inspection after trenches are excavated and forms erected (including a form-board survey for one- and two-family homes verifying the structure sits per the site plan); a framing inspection once the roof deck, framing, fireblocking and bracing are in place and rough openings are verified; a sheathing inspection covering roof and wall sheathing, fasteners and dry-in; an exterior wall coverings inspection for veneers and soffits; a roofing inspection covering dry-in, insulation, coverings and flashing; and a final inspection once the building is complete and ready for occupancy.

Parallel inspection sequences apply to electrical, plumbing, mechanical and gas systems, each running from an underground or rough-in stage through a final inspection. Swimming pools get their own two-step sequence, after excavation and reinforcing steel, then a final inspection confirming required enclosure features, and demolition and manufactured-building projects each have dedicated inspection points. 5 to request each inspection and keep the work exposed and accessible until it is approved.

Violations & Fines

Concealing or covering work before the required inspection is approved is a code violation under Section 114.1, chargeable as a misdemeanor with each day of continued noncompliance treated as a separate offense. The building official may also require exposed work to be uncovered again for inspection at the owner's expense, and Chapter 162, Florida Statutes code-enforcement penalties apply for unpermitted work.

Frequently Asked Questions

What happens if I cover work before it's inspected?
You're in violation of Sections 110.1 and 110.3, which require work to stay exposed until approved. The building official can require you to uncover it again at your own expense, and continuing to build over unapproved work is chargeable as a misdemeanor under Section 114.1.
Who schedules building inspections in Alachua County?
Section 110.5 puts the duty on the permit holder or their authorized agent to notify the building official when work is ready. The official then determines the timing and sequencing of the actual inspection under Section 110.3.
Are pool inspections different from house inspections?
Yes. Swimming pools get a dedicated two-step sequence under Section 110.3 item 7: a first inspection after excavation and installation of reinforcing steel, bonding and the main drain, and a final inspection confirming the pool and its required safety enclosure are complete.
Does an approved inspection excuse a code violation?
No. Section 110.1 states an inspection approval is not construed as approval of a violation of this code or other county ordinances, so the building official can still require correction even after a passed inspection.

Sources & Official References

Other rules in Alachua County

All Alachua County rules

Florida rules heatmap·Compare Alachua County to another location·View the Florida building safety overview

Get notified when Building Inspections in Alachua County, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.