Greenwood County, SC Building Safety: Building Inspections (2026)
Key Facts
- Process
- Temporary certificate, then final certificate
- Temporary certificate
- Issued after county inspects electrical system
- Final certificate deadline
- Apply within 90 days of temporary certificate
- Final certificate
- Requires full code compliance inspection
- Consequence of delay
- Notice of revocation, power disconnected
- Enforcing official
- City/county building official
Summary
Greenwood County Code § 6-1-3 requires builders to obtain a temporary electrical certificate after county inspection and approval, then a final certificate once the completed building passes inspection for full code compliance. Missing deadlines triggers revocation and power disconnection.
In addition to any other permits required by this Code or other laws, all building contractors and other persons constructing buildings (collectively referred to in this section as builders) shall obtain both of the following electrical certificates:(1)Temporary certificate. After installation of the electrical system in a building, a builder shall apply to the county for a temporary certificate. Upon inspection and approval by the county of the electrical system of the building, the county shall issue a temporary certificate to and in the name of the builder. The temporary certificate shall authorize the electric utility company to supply electrical power to the building on a temporary basis during construction and subject to final inspection and approval by the county. ... (2)Final certificate. Upon completion of the building, a builder shall apply to the county for a final certificate. Upon inspection and determination by the county that the building complies with all applicable technical codes, regulations and ordinances, the county shall issue a final certificate to and in the name of the owner of the building.
Full Breakdown
Greenwood County ties its building inspection process to the electrical certificate procedure set out at Greenwood County Code § 6-1-3. After a builder installs the electrical system in a new or altered building, the builder must apply to the county for a temporary certificate; only after the county inspects and approves the electrical system does it issue that temporary certificate, which lets the electric utility connect power on a temporary basis while construction continues. Once the building is complete, the builder must apply again for a final certificate; the county issues it only after inspecting the building and determining it complies with all applicable technical codes, regulations and ordinances, and that final certificate is what lets the utility transfer service from the builder's name into the owner's name.
A builder who fails to apply for the final certificate within 90 days of the temporary certificate being issued, or who fails to correct defects or code violations within the time the county directs, faces revocation: the county issues a notice of revocation, the electric utility disconnects power, and the builder forfeits the right to obtain future temporary certificates. The city and county building official conducts both inspections and administers the certificate process for every technical code the county has adopted, and the board of planning and zoning appeals hears disputes that arise under it.
Violations & Fines
Occupying or using a building before the county issues the final inspection certificate, or failing to apply for that certificate within 90 days of the temporary certificate, triggers revocation under § 6-1-3: the county cancels the temporary certificate, the electric utility disconnects power, and the builder loses the right to obtain future temporary certificates until outstanding code violations are corrected.
Frequently Asked Questions
How does the building inspection process work in unincorporated Greenwood County?
What happens if I don't apply for the final inspection certificate in time?
Who inspects buildings in unincorporated Greenwood County?
Sources & Official References
Other rules in Greenwood County
Compare Greenwood County to another location·View the South Carolina building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.