Greenwood, IN Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Required inspections
Footing, rough-in and final
Governing section
Greenwood General Ordinances § 7-13
Permit term
365 days, one extension available
Construction start deadline
45 days from permit issuance
First-offense fine
$50, then $50 per day
Enforcing office
Building Commissioner, Community Development Services

Summary

The City of Greenwood, Indiana requires the Building Commissioner to inspect every permitted construction project at a minimum of three stages: footing, rough-in and final. Permit holders must notify the Building Commissioner's office in Community Development Services when the work is ready for each inspection, and a certificate of occupancy cannot issue until the final inspection is complete.

After the issuance of any building permit hereunder, the Building Commissioner shall make, or shall cause to be made, such inspections of the work being done under such permit as are necessary to insure full compliance with the provisions of this Article and the terms of the permit. It shall be the responsibility of the person or persons obtaining a permit to notify the Building Commissioner that the building or structure for which the permit has been obtained is ready for inspection. The permit holder shall notify the Building Commissioner for a minimum of three (3) inspections: (a) Footing; (b) Rough-in; and (c) Final.

Full Breakdown

Section 7-13 of the Greenwood General Ordinances directs the Building Commissioner to make, or cause to be made, whatever inspections are necessary to confirm that work under a building permit complies with the Article and the permit's terms. The ordinance places the notification burden on the permit holder, who must tell the Building Commissioner when the building or structure is ready, and requires a minimum of three inspections: footing, rough-in, and final. Permits themselves run for 365 days from issuance under Section 7-11(b), with one 365-day extension available at half the original base permit fee if there is sufficient evidence the project will finish in that time; construction must start within forty-five days of issuance, and the Building Commissioner may revoke a permit and pursue enforcement under Section 7-24 if work sits inactive for more than ninety days or the project is abandoned or left blighted.

No certificate of occupancy may issue under Section 7-15 until the final inspection confirms the structure was built, altered or repaired in compliance with the Article, and occupying a building before that certificate is issued is unlawful. Fees for permits and inspections follow the schedule the Common Council adopted in Section 4-66, and building without first obtaining the required permit doubles the fee owed. Decisions of the Building Commissioner may be appealed first to the Plan Commission and then to the Indiana Fire Prevention and Building Safety Commission under Section 7-17.

Violations & Fines

Violating the permit or inspection requirements of Article 1 is an offense under Section 7-18: a first violation draws a fifty dollar fine, and each day a violation continues after notice is served is a separate fifty-dollar-per-day offense. A repeat violation within two years of a prior conviction is fined one hundred dollars per day, and the Building Commissioner may also deny future permits or inspections or revoke an issued permit.

Frequently Asked Questions

How many inspections does Greenwood require during construction?
Section 7-13 requires a minimum of three inspections after a building permit is issued: footing, rough-in, and final. The permit holder, not the city, is responsible for notifying the Building Commissioner when the work is ready for each stage, and the Commissioner may schedule additional inspections as needed to confirm compliance with the permit's terms.
Can I get a certificate of occupancy before the final inspection?
No. Section 7-15 bars issuing a certificate of occupancy for any building erected, altered or repaired after December 22, 1981 unless it complies with Article 1, and the permit holder must request the final inspection before occupying the structure. Occupying it without a certificate of occupancy is unlawful under the same section.
What happens if I start construction without a permit?
Section 7-11(a) requires a permit before construction begins, and Section 7-14 doubles the permit fee for anyone who starts work before obtaining it. Continuing without complying can also trigger the Section 7-18 penalties: a fifty dollar fine for a first offense and a daily fifty dollar fine for each day the violation continues after notice.

Sources & Official References

Other rules in Greenwood

All Greenwood rules

Compare Greenwood to another location·View the Indiana building safety overview

Get notified when Building Inspections in Greenwood, IN changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.