Key Facts

Required inspections
Foundation, framing, insulation, lath/wallboard, final
Inspection request notice
At least one workday in advance
Enforcing agency
Henderson Building & Fire Safety Department
Max penalty
$1,000 fine, 6 months jail
Final inspection
Required before any occupancy or use

Summary

Henderson requires five inspection stages for permitted construction, foundation, framing, insulation, lath/wallboard, and final, before work can be covered or the building occupied, per Municipal Code § 15.01.340.

Reinforcing steel or structural framework of any part of any building or structure shall not be covered or concealed without first obtaining the approval of the building official. Upon receipt of a proper inspection request, the building official shall perform the following inspections: A.Foundation inspection... B.Framing inspection... C.Insulation inspection... D.Lath and/or wallboard inspection... F.Final inspection...

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 59 Update 3).

Full Breakdown

Henderson's building official performs five mandatory inspections on permitted work: foundation (after excavation and rebar placement, before the concrete pour), framing (after structural framing and rough utilities are in), insulation, lath/wallboard, and final (before any occupancy or use). Reinforcing steel and structural framework cannot be covered or concealed without prior approval. Inspection requests must be filed at least one workday in advance under § 15.01.335, and any work that fails inspection must be corrected and re-inspected before it can be concealed. Freestanding walls and fences six feet or less are exempt from final inspection.

Violations & Fines

Covering or concealing work before the building official approves it, or proceeding beyond an inspected stage without approval, is a misdemeanor under § 15.01.120: up to a $1,000 fine and six months in jail, plus reinspection fees.

Frequently Asked Questions

What inspections does Henderson require during construction?
Foundation, framing, insulation, lath/wallboard, and final inspections, plus applicable electrical, plumbing or mechanical inspections, per Henderson Municipal Code § 15.01.340.
How much advance notice do I need to request an inspection?
At least one workday. Requests filed later than that are deemed improper notice and rescheduled to the next workday under § 15.01.335.
Can I cover framing or foundation work before it's inspected?
No. Reinforcing steel and structural framework cannot be concealed until the building official approves that inspection stage, per § 15.01.335 and § 15.01.340.

Sources & Official References

Other rules in Henderson

All Henderson rules

Compare Henderson to another location·View the Nevada building safety overview

Get notified when Building Inspections in Henderson, NV changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Nearby Cities

How other cities in Clark County handle building inspections.

North Las Vegas, NV
Some Restrictions