Key Facts

Inspection stages
Foundation, slab/under-floor, frame, insulation, lath, final
Notice required
1 working day, § 15.72.180.C
Work-stoppage rule
No progress past called inspection without approval
Occupancy requirement
Final inspection mandatory, § 15.72.180.E.6
Reinspection fee
Applies on repeat failures, not first rejection

Summary

North Las Vegas requires a series of called inspections for any permitted construction, from foundation through final, under § 15.72.180 of the Building Administrative Code. Work can't be covered or concealed until the Building Official signs off on each stage, and a final inspection is mandatory before a building can be occupied.

1.Foundation Inspection. To be made after excavations for footings are complete and required reinforcing steel is in place. ... 3.Frame Inspection. ... a.For wood and light gauge metal construction: To be performed after the roof sheathing, all framing, fire blocking and bracing are in place and all pipes, chimneys and vents to be concealed are complete and the rough electrical, plumbing, and mechanical inspections are approved. ... 6.Final Inspection. To be made after finish grading and the building is completed and ready for occupancy.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 146 Update 1).

Full Breakdown

D bars any work from proceeding past the point of a called inspection until the Building Official approves it, and reinforcing steel or structural framing may not be covered until that approval is given. H when work isn't ready at the scheduled time or corrections weren't made, though the code specifies no fee applies the first time a job is simply rejected for noncompliance.

Violations & Fines

Covering or concealing work, pouring a slab, closing up framing, before the required inspection is approved violates § 15.72.180.D and can force the Building Official to require the covering material removed at the owner's expense to permit inspection. Continued unpermitted or uninspected construction is prosecuted as a misdemeanor under § 15.72.160.H, punishable by up to a $1,000 fine, six months in jail, or both.

Frequently Asked Questions

What inspections does North Las Vegas require during a home build?
Six called inspections under § 15.72.180.E: foundation, concrete slab or under-floor, frame, insulation, lath/wallboard, and a final inspection before the building can be occupied. Each must be approved before the next phase of work covers it up.
How much notice do I need to give before requesting an inspection?
The Building Official can require inspection requests to be filed at least one working day before the inspection is wanted, per § 15.72.180.C, and the request can be made in writing, by computer, or by phone at the Building Official's option.
Can I be charged for a failed inspection?
Only on a repeat visit. § 15.72.180.H allows a reinspection fee when work isn't ready or required corrections weren't made, but the code specifically says a fee doesn't apply 'the first time a job is rejected for failure to comply' with the technical codes.

Sources & Official References

Other rules in North Las Vegas

All North Las Vegas rules

Compare North Las Vegas to another location·View the Nevada building safety overview

Get notified when Building Inspections in North Las Vegas, NV changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Nearby Cities

How other cities in Clark County handle building inspections.

Henderson, NV
Some Restrictions