Key Facts

Occupancy requirement
Certificate of occupancy mandatory
Final CO sign-off
Requires fire chief approval
Electrical inspection
No concealing wiring before approval
Building code applied
MUBEC via 25 M.R.S. § 2373
Base penalty
$200–$2,500 per day

Summary

No building, structure, or property in Portland may be used or occupied without a certificate of occupancy. City Code § 6-93 blocks a final certificate unless the property fully complies with the Code and the fire chief or designee has approved it, tying occupancy to a completed inspection chain.

(a) No building, structure, or property shall be used or occupied without a certificate of occupancy. (b) No final certificate of occupancy shall be issued where any condition of the building, structure, or property is not in compliance with any other section of this Code, except where phased occupancy is specifically provided for in approved permits or plans. (c) No final certificate of occupancy shall be issued without the approval of the fire chief or his or her designee.

View official code

Official source re-checked September 7, 2026: the cited page had not changed since it was quoted.

Full Breakdown

Chapter 6, Article II, Division 1 of the Portland Code of Ordinances (Ord. 18-17/18, 8-21-2017) runs the city's building inspection process from permit to occupancy. § 2373. For electrical work specifically, § 6-101 gives the building authority the right, during reasonable hours, to enter any premises to inspect, reinspect, or test wiring, devices, appliances, and equipment; wiring may not be covered or concealed until it has been inspected and approved, and a "closing-in inspection" requires wall boxes and neutral/bonding wires to be made ready before the inspection is called.

The building authority can reject work that fails to meet the permit or applicable code, or that isn't done in a workmanlike, safe manner. The process culminates in § 6-93: no building, structure, or property may be used or occupied without a certificate of occupancy, no final certificate issues while any part of the property is out of compliance with the Code (unless a permit or plan specifically authorizes phased occupancy), and no final certificate of occupancy issues without the fire chief's or designee's sign-off.

Violations & Fines

Occupying a structure without a certificate of occupancy, or covering inspected work before approval, exposes the owner to the general Chapter 6 penalty scale in § 6-1: a minimum $200/day (up to $2,500/day) for a significant code violation, rising to a $500–$5,000/day range after a written correction notice and $1,500–$10,000/day after a second notice, plus possible suspension of permitting privileges for contractors, owners, or developers.

Frequently Asked Questions

Can I occupy a Portland building before it's inspected?
No. Section 6-93 states no building, structure, or property shall be used or occupied without a certificate of occupancy, and the city withholds a final certificate until the property complies with the Code, unless a permit specifically allows phased occupancy.
Who signs off on a final building inspection in Portland?
The Permitting and Inspections Department Director, acting as building authority, oversees Code enforcement inspections, but § 6-93(c) requires fire chief or designee approval before any final certificate of occupancy can issue.
Can I cover electrical wiring before it's inspected?
No. Section 6-101(b) prohibits covering or concealing wiring or other electrical work requiring a permit before the building authority has inspected or approved it, and a closing-in inspection must be called once boxes and bonding are ready.

Sources & Official References

Other rules in Portland

All Portland rules

Compare Portland to another location·View the Maine building safety overview

Get notified when Building Inspections in Portland, ME changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.