Key Facts
- Foundation inspection
- Before concrete is poured (§ 109.1)
- Rough inspection
- Before covering plumbing/mechanical/electrical (§ 109.1.2)
- Frame/masonry inspection
- After rough inspections pass (§ 109.1.4)
- Final inspection
- After work complete, before occupancy (§ 109.1.6)
- Inspection request
- Permit holder must request each one (§ 109.3)
- Penalty for covering unapproved work
- $100-$500 fine
Summary
Building work in unincorporated Rapides Parish moves through a sequence of required inspections under § 109 of the parish's administrative building code: foundation, slab or under-floor, rough plumbing/mechanical/gas/electrical, framing and masonry, and a final inspection before occupancy. The permit holder must request each inspection, and covering work before it is approved violates the code.
109.1 Foundation Inspection - Inspection of the foundation shall be made after poles or piers are set or trenches or basement areas are excavated and any required forms erected and any required reinforcing steel is in place and supported prior to the placement of concrete. The foundation inspection shall include excavations for thickened slabs intended for the support of bearing walls, partitions, structural supports, or equipment and special requirements for wood foundations. ... 109.1. ... 6 Final inspection - Final inspection shall be made after the permitted work is complete and prior to occupancy.
Full Breakdown
Section 6½-10's Section 109 lays out the inspection sequence the building official follows for permitted work in the unincorporated parish. 1 happens after piers or trenches are excavated, forms are erected, and reinforcing steel is placed and supported, but before concrete is poured; it also covers excavations for thickened slabs supporting bearing walls or equipment. 1 follows, after in-slab or under-floor reinforcing steel and utility rough-in are in place but before concrete is placed or the subfloor is installed. 2 must happen before any of that work is covered or concealed, before fixtures or appliances are set, and before the framing inspection.
4 comes after the roof, masonry, framing, fire stopping, draft stopping and bracing are all in place and after the rough plumbing, mechanical and electrical inspections have passed. 5 requires an inspection after lathing or wallboard is up but before plaster or taping and finishing. 3, requiring a sealed elevation certificate from a registered design professional once the lowest floor is placed and before further vertical construction. 6 happens after all permitted work is complete and before the structure is occupied. 4 bars proceeding past any inspection point until the building official approves it.
Violations & Fines
Covering or concealing work before the building official has inspected and approved that stage violates § 109.4, and any portion that fails to comply must be corrected and re-exposed before it can be covered again. Because inspections enforce the same administrative building code adopted at § 6½-10, a violation carries the general penalty at § 6½-8: a fine of not less than $100 nor more than $500 per offense for the responsible person, partnership or corporation.
Frequently Asked Questions
What inspections does a new house in Rapides Parish need before the walls are closed up?
Who has to call for a building inspection in Rapides Parish?
What is the last inspection before I can move into a new building in Rapides Parish?
Sources & Official References
Other rules in Rapides Parish
Compare Rapides Parish to another location·View the Louisiana building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.