Key Facts

Inspection duty
Work stays exposed until inspected (§ 137-5A)
Stages inspected
Footing, framing, systems, final, etc.
Energy Code check
Listed inspection element, § 137-5B(9)
Outcome of failed inspection
Work stays exposed until corrected
Fee
Paid before or at each inspection (§ 137-16)

Summary

Once Schenectady issues a building permit, work must stay exposed and accessible for inspection at each construction stage, from footings and framing through a final inspection, and the Code Enforcement Officer must sign off before the permitted work is considered complete.

§ 137-4. Building permits. ... F. Issuance of building permits. An application for a building permit shall be examined to ascertain whether the proposed work is in compliance with the applicable requirements of the Uniform Code and Energy Code. The Code Enforcement Officer shall issue a building permit if the proposed work is in compliance with the applicable requirements of the Uniform Code and Energy Code. ... § 137-5. Construction inspections. A. Work to remain accessible and exposed. Work shall remain accessible and exposed until inspected and accepted by the Code Enforcement Officer or by an inspector authorized by the Code Enforcement Officer. ... B. Elements of work to be inspected. The following elements of the construction process shall be inspected, where applicable: (1) Work site prior to the issuance of a building permit; (2) Footing and foundation; (3) Preparation for concrete slab; (4) Framing; ... (10) A final inspection after all work authorized by the building permit has been completed.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4990798; v11 updated 2026-04-13; through 04-13-2026).

Full Breakdown

Chapter 137 sets out a two-step process: permit issuance under § 137-4, then a defined inspection sequence under § 137-5. Section 137-4F requires the Code Enforcement Officer to examine an application to determine whether the proposed work complies with the Uniform Code and Energy Code, and directs that a permit be issued once it does. After the permit issues, § 137-5A requires that the work remain accessible and exposed until it is inspected and accepted by the Code Enforcement Officer or an authorized inspector, and puts the burden on the permit holder to notify the Officer when each element of work is ready for inspection.

Subsection B lists the specific stages that must be inspected where applicable: the work site itself before a permit issues, footing and foundation, preparation for a concrete slab, framing, building systems including underground and rough-in work, fire-resistant construction and fire-resistant penetrations, solid-fuel-burning heating appliances, chimneys, flues or gas vents, Energy Code compliance, and a final inspection after all permitted work is complete. Section 137-5C describes the outcome of each inspection: the work is noted satisfactory as completed, or the permit holder is told where it fails to comply, and noncompliant work must remain exposed until it is corrected, reinspected, and found satisfactory.

A fee set under § 137-16, Fees, must be paid before or at the time of each inspection. Beyond construction inspections, the Code Enforcement Officer separately conducts recurring firesafety and property maintenance inspections under § 137-12, at intervals ranging from every 12 months for public-assembly buildings and dormitories to every 36 months for other multiple dwellings and nonresidential buildings.

Violations & Fines

Concealing or covering work before it has been inspected and accepted violates § 137-5A, and noncompliant work must remain exposed until corrected and reinspected. General Chapter 137 violations, including inspection failures left uncorrected, carry a civil penalty of not more than $200 per day under § 137-16C.

Frequently Asked Questions

Can I cover up framing before the City inspects it?
No. Section 137-5A requires work to remain accessible and exposed until it has been inspected and accepted by the Code Enforcement Officer or an authorized inspector; the permit holder must request each inspection.
What construction stages does Schenectady inspect?
Section 137-5B lists the work site, footing and foundation, concrete slab preparation, framing, building systems, fire-resistant construction and penetrations, solid-fuel heating appliances, Energy Code compliance, and a final inspection.
What happens if my work fails inspection?
Under § 137-5C, the Code Enforcement Officer notifies the permit holder where the work fails to comply, and the noncompliant work must remain exposed until it is brought into compliance, reinspected, and found satisfactory.
Do I have to pay for each building inspection?
Yes. Section 137-5D requires the fee set under § 137-16 to be paid prior to or at the time of each inspection performed under this section.

Sources & Official References

Other rules in Schenectady

All Schenectady rules

New York rules heatmap·Compare Schenectady to another location·View the New York building safety overview

Get notified when Building Inspections in Schenectady, NY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.