Walton County, FL Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Inspection list length
15 required inspection stages, Sec. 6-35
First stage
Footing, foundation
Final stage
Certificate of occupancy or completion
Waiver authority
Building official, Sec. 6-36
Appeal body
Board of adjustments/code enforcement board, Sec. 6-37

Summary

Walton County lists 15 required inspections for construction in the unincorporated county, running from footing and foundation through framing, electrical, plumbing, gas, mechanical and swimming pool work to the final certificate of occupancy. The building official can waive or combine inspections with proof of code compliance, and a rejected owner has the right to appeal.

These county ordinances apply to unincorporated areas of Walton County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

The following are required inspections for the county: (1)Footing, foundation.(2)Plumbing rough-in and plumbing.(3)Slab.(4)Monolithic slab.(5)Framing, floor, walls, roof.(6)Power (main entrance).(7)Final—Certificate of occupancy or certificate of completion.(8)Trailer pole inspection.(9)Temporary pole inspection.(10)Electrical inspection on signs.(11)Swimming pool inspections.(12)Electrical changeover (service).(13)Gas inspection.(14)Mechanical rough-in and mechanical.(15)Electrical rough-in and electrical. ... Whenever the building official shall reject or refuse to approve the mode or manner of construction or shall reject or refuse to waive or allow a combination inspection, the owner of a building or structure shall have the right to appeal to the board after the decision is rendered by the building official.

Full Breakdown

Section 6-35 sets out the required inspections for the county as a numbered list: footing and foundation; plumbing rough-in and plumbing; slab; monolithic slab; framing, floor, walls, roof; power at the main entrance; the final inspection for a certificate of occupancy or certificate of completion; trailer pole and temporary pole inspections; electrical inspection on signs; swimming pool inspections; electrical changeover of service; gas inspection; mechanical rough-in and mechanical; and electrical rough-in and electrical. Section 6-36 gives the building official discretion to waive an inspection based on test reports or proof of alternate materials and methods, and to waive or allow combination inspections when sufficient evidence of code compliance is submitted; that official holds the same powers and duties over inspections as the building official under Section 102 of the Standard Building Code in force in the county.

Section 6-37 then gives the owner a right of appeal: whenever the building official rejects or refuses to approve a mode or manner of construction, or refuses to waive or allow a combination inspection, the owner may appeal in writing, on the county's forms, to the board of adjustments/code enforcement board, which is designated the appeals board under Ordinance No. 96-19. Reinspection fees, assessed on a per-trip, per-trade basis under Section 6-29(b)(7), apply whenever work fails one of these required inspections and has to be checked again.

Violations & Fines

Failing a required inspection under Section 6-35 means the job cannot advance to the next construction stage, such as covering framing before it passes, and each reinspection carries its own per-trip, per-trade fee under Section 6-29(b)(7). Proceeding past a required inspection point without the sign-off exposes the work to a stop-work order from the building official.

Frequently Asked Questions

What inspections does Walton County require during a residential build?
Section 6-35 lists 15 required stages, including footing and foundation, slab or monolithic slab, framing, floor, walls and roof, power at the main entrance, plumbing, gas, mechanical and electrical rough-ins, swimming pool inspections, and the final inspection for a certificate of occupancy or completion.
Can the county waive a required inspection?
Yes. Section 6-36 lets the building official waive an inspection based on test reports or proof of alternate materials and methods, and waive or allow a combination inspection, as long as the applicant submits sufficient evidence that the work complies with the adopted codes.
What can I do if the building official rejects my construction method?
Section 6-37 gives the owner the right to appeal in writing, on forms the building official provides, to the county board of adjustments/code enforcement board, which is designated as the appeals board for these decisions under Ordinance No. 96-19.

Sources & Official References

Other rules in Walton County

All Walton County rules

Florida rules heatmap·Compare Walton County to another location·View the Florida building safety overview

Get notified when Building Inspections in Walton County, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.