Walton County, FL Building Safety: Building Inspections (2026)
Key Facts
- Inspection list length
- 15 required inspection stages, Sec. 6-35
- First stage
- Footing, foundation
- Final stage
- Certificate of occupancy or completion
- Waiver authority
- Building official, Sec. 6-36
- Appeal body
- Board of adjustments/code enforcement board, Sec. 6-37
Summary
Walton County lists 15 required inspections for construction in the unincorporated county, running from footing and foundation through framing, electrical, plumbing, gas, mechanical and swimming pool work to the final certificate of occupancy. The building official can waive or combine inspections with proof of code compliance, and a rejected owner has the right to appeal.
The following are required inspections for the county: (1)Footing, foundation.(2)Plumbing rough-in and plumbing.(3)Slab.(4)Monolithic slab.(5)Framing, floor, walls, roof.(6)Power (main entrance).(7)Final—Certificate of occupancy or certificate of completion.(8)Trailer pole inspection.(9)Temporary pole inspection.(10)Electrical inspection on signs.(11)Swimming pool inspections.(12)Electrical changeover (service).(13)Gas inspection.(14)Mechanical rough-in and mechanical.(15)Electrical rough-in and electrical. ... Whenever the building official shall reject or refuse to approve the mode or manner of construction or shall reject or refuse to waive or allow a combination inspection, the owner of a building or structure shall have the right to appeal to the board after the decision is rendered by the building official.
Full Breakdown
Section 6-35 sets out the required inspections for the county as a numbered list: footing and foundation; plumbing rough-in and plumbing; slab; monolithic slab; framing, floor, walls, roof; power at the main entrance; the final inspection for a certificate of occupancy or certificate of completion; trailer pole and temporary pole inspections; electrical inspection on signs; swimming pool inspections; electrical changeover of service; gas inspection; mechanical rough-in and mechanical; and electrical rough-in and electrical. Section 6-36 gives the building official discretion to waive an inspection based on test reports or proof of alternate materials and methods, and to waive or allow combination inspections when sufficient evidence of code compliance is submitted; that official holds the same powers and duties over inspections as the building official under Section 102 of the Standard Building Code in force in the county.
Section 6-37 then gives the owner a right of appeal: whenever the building official rejects or refuses to approve a mode or manner of construction, or refuses to waive or allow a combination inspection, the owner may appeal in writing, on the county's forms, to the board of adjustments/code enforcement board, which is designated the appeals board under Ordinance No. 96-19. Reinspection fees, assessed on a per-trip, per-trade basis under Section 6-29(b)(7), apply whenever work fails one of these required inspections and has to be checked again.
Violations & Fines
Failing a required inspection under Section 6-35 means the job cannot advance to the next construction stage, such as covering framing before it passes, and each reinspection carries its own per-trip, per-trade fee under Section 6-29(b)(7). Proceeding past a required inspection point without the sign-off exposes the work to a stop-work order from the building official.
Frequently Asked Questions
What inspections does Walton County require during a residential build?
Can the county waive a required inspection?
What can I do if the building official rejects my construction method?
Sources & Official References
Other rules in Walton County
Florida rules heatmap·Compare Walton County to another location·View the Florida building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.