Key Facts

Governing section
Town Code § 180-22
Permit issued by
Division of Building
Application signed by
Licensed master plumber
Also needs permit
Sprinkler systems, underground irrigation
Repairs exempt
Fixture swaps, not new piping
Penalty
Up to $350 fine or 15 days

Summary

Town Code § 180-22 requires a plumbing permit from the Division of Building before any new plumbing, drainage or sewage work, signed off by a licensed master plumber, in every building or structure in the Town of Oyster Bay.

It shall be unlawful to perform any plumbing, drainage or sewage work in a building or structure or to extend or alter any existing plumbing or drainage work or connect any public sewer system to a private sewer, drain pit, filter bed, leaching well, septic tank or other receptacle or install a fuel storage tank inside or outside of a building unless a permit has been obtained from the Division of Building of the Department of Planning and Development.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4036544; v24 updated 2023-03-07; through 03-07-2023).

Full Breakdown

Section 180-22, in the Plumbing chapter's Article IV, sets the permit trigger for essentially all plumbing work in the Town. Subsection A requires that 'at the time of filing an application for a building permit, each applicant shall include an application for a plumbing permit properly signed by a master plumber,' with the fee set by the Commissioner of the Department of Planning and Development under the chapter's fee schedule, § 180-9. Subsection B makes the permit mandatory across the board: it is unlawful to perform plumbing, drainage or sewage work, extend or alter existing plumbing, connect a public sewer to a private sewer, drain pit, filter bed, leaching well or septic tank, or install a fuel storage tank inside or outside a building without a Division of Building permit, though ordinary repairs or fixture replacement are exempted as long as they don't amount to installing new soil, waste, vent pipe or main house drains.

A separate permit is required for any sprinkler fire-protection piping system, and for any underground irrigation system, tying this section back to the Water Conservation rules in § 180-11. Section 180-23 requires the application to be filed by a licensed master plumber on Division of Building forms, and § 180-5 ties all installation work to the state Uniform Fire Prevention and Building Code standard. The Plumbing Inspector, an assistant to the Commissioner under § 180-16, reviews applications, inspects work in progress, and reports violations to the Commissioner for enforcement. 1.

Violations & Fines

Performing plumbing, drainage or sewage work, or installing a sprinkler or irrigation system, without the § 180-22 permit is punishable under § 180-20 by a fine up to $350, up to fifteen days' imprisonment, or both, per offense; the owner, contractor, architect or any assisting party can each be separately charged.

Frequently Asked Questions

Do I need a permit to replace a broken toilet or sink?
No. Section 180-22B(1) exempts repairs to existing plumbing or drainage systems and the replacement of existing fixtures from the permit requirement, as long as the work doesn't amount to installing new soil, waste or vent pipe or a main house drain, which do require a permit.
Who signs my Oyster Bay plumbing permit application?
A licensed master plumber. Section 180-22A requires the plumbing permit application to be filed alongside your building permit application and 'properly signed by a master plumber,' and § 180-23 requires it to be submitted on Division of Building forms by that licensed plumber.
Does installing a sprinkler system or lawn irrigation need a separate permit?
Yes. Section 180-22B(2) requires a Division of Building permit before installing any fire-sprinkler piping system, and § 180-22B(4) separately requires a building permit before installing any underground irrigation system, tying the permit rule directly to the Town's water-conservation restrictions in § 180-11.

Sources & Official References

Other rules in Oyster Bay

All Oyster Bay rules

New York rules heatmap·Compare Oyster Bay to another location·View the New York building safety overview

Get notified when Plumbing Permits in Oyster Bay, NY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.