Key Facts

Governing section
City Code § 30-6
Permit issuer
City Manager
Permit duration
Up to one year per location
Insurance minimum
$100,000/person, $500,000/occurrence
Property damage minimum
$100,000, or $750,000 combined
General penalty
Class 3 misdemeanor, § 30-1

Summary

Before a contractor can erect scaffolding, cranes, hoists or similar equipment over a Roanoke street, alley or sidewalk for construction, demolition or cleaning work, City Code § 30-6 requires a permit from the city manager plus proof of public liability insurance filed with the city clerk covering injury, death and property damage.

When construction, demolition, cleaning, or similar operations on private property are authorized under this Code to be permitted, in whole or in part, from or upon portions of public streets, alleys, sidewalks or other public ways...and such operations involve or require the use of machinery or equipment, such as, but not limited to elevators, cranes, derricks, scaffolds, framework, aerial platforms, hoists, and similar equipment...no such operations shall be performed until a permit is issued therefor by the city manager. Such permits may cover operations for up to one (1) year at a given location...No such operations shall be performed until the person directly responsible for the performance of the same has filed with the city clerk...written evidence of standard form public liability insurance, insuring such person against liability for personal injury or death, for not less than one hundred thousand dollars ($100,000.00) for any one (1) person and not less than five hundred thousand dollars ($500,000.00) for any one (1) accident or occurrence, and for not less than one hundred thousand dollars ($100,000.00) for property damage.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 94 Update 1).

Full Breakdown

City Code § 30-6 governs any time a private construction, demolition or cleaning project needs to use public streets, alleys, sidewalks or other public ways, whether or not they are closed to traffic during the work. It specifically covers equipment operated in or over those public ways, or extended out over them, including elevators, cranes, derricks, scaffolds, framework, aerial platforms and hoists, along with similar equipment. No such operation may begin until the city manager issues a permit for it, and a single permit can authorize up to one year of work at a given location before it must be renewed.

Before the permit-holder can start work, the person directly responsible for the operation must file written evidence with the city clerk of standard-form public liability insurance from a company licensed to do business in Virginia. The policy has to cover personal injury or death for at least $100,000 per person and at least $500,000 per accident or occurrence, and property damage of at least $100,000, or a combined single-limit policy of at least $750,000. This insurance requirement sits on top of, not in place of, any other bond or security the Code requires elsewhere, such as the building-operations bond referenced at § 7-3. The city manager also has authority to write reasonable regulations governing how these operations are conducted so they do not endanger public health, welfare or safety, meaning a contractor working from a sidewalk scaffold can be held to additional site-specific rules beyond the base permit and insurance requirements.

Violations & Fines

Performing scaffold, crane, hoist or similar work over a Roanoke public street, alley or sidewalk without the § 30-6 permit, or without filing the required liability insurance evidence with the city clerk first, means the work was never authorized to begin. Chapter 30's general penalty at § 30-1 makes an unpermitted violation of this chapter a Class 3 misdemeanor, and the city manager can also require the operation to stop until a permit and insurance are in place.

Frequently Asked Questions

Do I need a city permit to put up a scaffold over the sidewalk?
Yes. City Code § 30-6 requires a permit from the city manager before any scaffold, crane, hoist, aerial platform or similar equipment is operated in or over a Roanoke street, alley or sidewalk in connection with construction, demolition or cleaning work, whether or not the public way is closed to traffic during the work.
How much liability insurance does a Roanoke scaffold permit require?
Before work starts, the responsible person must file written evidence with the city clerk of public liability insurance covering at least $100,000 per person and $500,000 per accident for injury or death, and at least $100,000 for property damage, or a combined policy of at least $750,000.
How long does a § 30-6 permit last?
A single permit issued under City Code § 30-6 can cover operations at a given location for up to one year before it needs to be renewed with the city manager.

Sources & Official References

Other rules in Roanoke

All Roanoke rules

Compare Roanoke to another location·View the Virginia building safety overview

Get notified when Scaffold & Sidewalk Shed in Roanoke, VA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.