Eagle Mountain, UT Building Setbacks & Zoning: Lot Coverage Limits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Applies to
Average lot slope between 8% and 25%
Best case
30% impervious, slope <=25%, slightly erodible soil
Mid case
20% impervious on moderately erodible soil
Worst case
5% impervious, slope <=15%, moderately erodible
Hard cap
1% impervious; no development above 25% slope

Summary

On lots with average natural slope between 8 and 25 percent, Eagle Mountain limits impervious coverage on a sliding scale by slope and soil erodibility: up to 30 percent on gentle, stable ground down to as little as 5 percent on steeper, more erodible ground, with development barred outright above 25 percent slope, under EMMC 16.40.090.

Property that has an average slope between eight and 25 percent shall comply with Diagram 16.40.090 and the following standards: A. Thirty Percent Impervious Lot Cover. A lot may be developed with 30 percent of the total lot area covered with impervious area if the average slope of the ground is 25 percent or less and the soils are only slightly erodible. ... ... C. Twenty Percent Impervious Lot Cover. A lot may be developed with 20 percent of the total lot area covered with impervious area under the following conditions: (1) if the average slope of the ground is 25 percent or less and the soils are moderately erodible; (2) if the average slope of the ground is 15 percent or less and the soils are erodible. ... ... E. One Percent Impervious Lot Cover. Development is prohibited on slopes greater than 25 percent.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance O-34-2026, passed August 4, 2026).

Full Breakdown

090 illustrates the same limits by slope and soil class. A lot with a slope of 25 percent or less on only slightly erodible soil may cover 30 percent of its area with impervious surface; on slightly-to-moderately erodible soil at the same slope the cap drops to 25 percent; on moderately erodible soil at 25 percent slope, or on erodible soil at 15 percent slope or less, it drops to 20 percent; on moderately erodible soil at 15 percent slope or less it falls to just 5 percent.

The code works the math for a 1,500-square-foot house with another 1,500 square feet of driveway, sidewalk and patio: that combination needs a 10,000-square-foot lot at the 30 percent tier but a 60,000-square-foot lot at the 5 percent tier. Above 25 percent average slope, development is prohibited outright and the effective impervious allowance is one percent. Section F explains why: steeper ground speeds up runoff and cuts infiltration, and sandy or silty soils erode easily because they lack clay to bind particles together, while clay-rich soils resist washing away. 040(E) before the city engineer will approve clearing, excavation or grading.

Violations & Fines

A development plan that exceeds the impervious cap for its lot's slope and soil class fails plan review under the runoff and erosion control plan required by EMMC 16.40.040 and will not receive city engineer approval to clear, excavate or grade under EMMC 16.40.030. On any portion of a lot where the natural slope equals or exceeds 25 percent, EMMC 16.40.070 separately bars excavation, grading or fill outright, regardless of the impervious percentage proposed.

Frequently Asked Questions

What if my lot's average slope is under 8 percent?
The sliding-scale limits of EMMC 16.40.090 govern only lots averaging between 8 and 25 percent slope; the code text ties the whole schedule and Diagram 16.40.090 to that band, so flatter and steeper lots fall outside this particular impervious-cover table.
Can I build at all on a slope over 25 percent?
No. Category E of EMMC 16.40.090 sets impervious cover at one percent because "development is prohibited on slopes greater than 25 percent," and EMMC 16.40.070 separately bars any excavation, grading or fill on the portion of a lot where the natural slope equals or exceeds 25 percent.
How much does soil type change my impervious limit?
On the same 25 percent slope, erodibility alone swings the allowance from 30 percent coverage on only slightly erodible soil down to 20 percent on moderately erodible soil, because sandy or silty soils erode easily for lack of clay to bind particles together, while clay-rich soils resist washing away.
What does the city require before I can start grading a sloped lot?
An excavation permit and a city engineer-approved clearing, excavation and grading plan under EMMC 16.40.030, plus a runoff and erosion control plan under EMMC 16.40.040(E) that demonstrates the proposed impervious area complies with EMMC 16.40.090 and Diagram 16.40.090.

Sources & Official References

Other rules in Eagle Mountain

All Eagle Mountain rules

Compare Eagle Mountain to another location·View the Utah building setbacks & zoning overview

Get notified when Lot Coverage Limits in Eagle Mountain, UT changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.