Stormwater Management

Dixmont's Site Plan Review Ordinance requires nonresidential and multifamily projects to collect and dispose of all stormwater through a drainage system and maintenance plan with no adverse impact on abutting or downstream properties. Post-development flow from the site cannot exceed the predevelopment rate, and natural drainage ways stay open unless the Planning Board approves otherwise.

Dixmont Site Plan Stormwater Management Standard

Some Restrictions

Dixmont Site Plan Review Ordinance § 9.7

9.7. Stormwater Management (AS) Adequate provisions must be made for the collection and disposal of all stormwater that runs off proposed streets, parking areas, roofs, and other surfaces, through a stormwater drainage system and maintenance plan, which must not have adverse impacts on abutting or downstream properties. 1) To the extent possible, the development must retain stormwater on the si...

Erosion Control

Inside Dixmont's shoreland zone, any permitted filling, grading or excavation that leaves soil unstabilized needs a written erosion and sedimentation control plan approved by the permitting authority. Exposed ground must be stabilized within one week of last work and permanently within nine months. Outside the shoreland zone, only nonresidential and multifamily projects under Site Plan Review face a separate erosion standard.

Dixmont Shoreland Erosion and Sedimentation Control

Some Restrictions

Dixmont Shoreland Zoning Ordinance § 15(T)(1), (4), (5)

(1) All activities which involve filling, grading, excavation or other similar activities which result in unstabilized soil conditions and which require a permit shall also require a written soil erosion and sedimentation control plan. The plan shall be submitted to the permitting authority for approval and shall include, where applicable, provisions for: ... (4) Any exposed ground area shall b...

Boat Dock Permits

Dixmont's Shoreland Zoning Ordinance limits a lot to one structure below the high-water line, with a Code Enforcement Officer permit for temporary piers and docks and a Planning Board permit for permanent ones. A temporary dock for non-commercial use cannot be wider than six feet. New permanent piers and docks are not permitted unless a temporary dock is shown to be infeasible and the state has issued a permit.

Dixmont Pier and Dock Permit Rules in the Shoreland Zone

Significant Restrictions

Dixmont Shoreland Zoning Ordinance § 15(C)(1), (5) and (7); Table 1, item 15

(1) No more than one structure extending or located below the normal high-water line of a water body or within a wetland is allowed on a single lot; except that when a single lot contains at least twice the minimum shore frontage as specified in Section 15(A), a second structure may be allowed and may remain as long as the lot is not further divided. ... (5) The facility shall be no larger in d...