Environmental Rules in Freehold Township, NJ (2026)
4 verified environmental rules for Freehold Township, New Jersey, sourced directly from the municipal code and official government pages.
Verified from official government sources
Stormwater Management
Major development in Freehold Township must meet the stormwater management standards in Code § 190-80, which requires green infrastructure to control erosion, groundwater recharge, runoff quantity and runoff quality. Projects must either preserve 100% of the site's pre-construction average annual groundwater recharge volume or infiltrate the increased two-year-storm runoff, and must strip 80% of total suspended solids from runoff generated by any net increase in motor vehicle surface.
Freehold Township Stormwater Management Rules
Some RestrictionsFreehold Township Code § 190-80
§ 190-80. Stormwater management. ... Purpose. The purpose of this section is to establish minimum stormwater management requirements and controls for "major development," as defined below in Subsection B. ... Demonstrate through hydrologic and hydraulic analysis that the site and its stormwater management measures maintain 100% of the average annual pre-construction groundwater recharge volume ...
Erosion Control
Freehold Township requires a Township Engineer-approved erosion and sediment control plan and a permit before any land area is disturbed by grading, excavation or clearing. Chapter 282 gives the Engineer 30 days to act on a complete application, and violators face Superior Court injunctions plus fines under the Township's general penalty ordinance.
Freehold Township Erosion and Sediment Control Permit
Some RestrictionsFreehold Township Code §§ 282-4, 282-6
No land area shall be disturbed by any person within the Township unless and until that person shall have first submitted to the Township Engineer a plan to provide for the prevention of soil erosion and the control of sediment for such land area consistent with the provisions of this chapter and such plan shall have been approved and a valid permit shall have been issued by the Township Engine...
Flood Zones
Freehold Township requires a floodplain development permit from the Township's Floodplain Administrator before any construction, filling, grading or land alteration in a mapped flood hazard area. Adopted in 2022 under Chapter 166, the ordinance layers onto FEMA and state flood-hazard mapping and carries fines up to $2,000 and 90 days for noncompliance.
Freehold Township Floodplain Development Permit
Some RestrictionsFreehold Township Code §§ 166-29, 166-8
Any person, owner or authorized agent who intends to conduct any development in a flood hazard area shall first make application to the Floodplain Administrator and shall obtain the required permit. Depending on the nature and extent of proposed development that includes a building or structure, the Floodplain Administrator may determine that a floodplain development permit or approval is requi...
Flood Elevation Requirements
New construction in a Freehold Township flood hazard area must have its lowest floor, including basement and all utilities, elevated to or above the local design flood elevation, a standard that adds at least one foot of freeboard above the base flood elevation under Township Code §§ 166-12 and 166-75.
Freehold Township Flood Elevation and Freeboard Rule
Some RestrictionsFreehold Township Code §§ 166-12, 166-75
At a minimum, the local design flood elevation shall be as follows: ... For a delineated watercourse, the elevation associated with the best available flood hazard data area determined in § 166-11, above plus one foot or as described by N.J.A.C. 7:13 of freeboard; or ... All new construction and substantial improvement of any habitable building (as defined in Article IX) located in flood hazard...