Fire Sprinkler Requirements
Pocatello's amended Fire Code does not require residential sprinklers citywide; instead, amended Section 602.1, adopted at City Code § 15.02.010, recommends an automatic sprinkler system for new buildings built to the Class 1 ignition-resistant construction standard inside a declared wildland-urban interface area. Outside a declared WUI area, or for construction not built to that standard, the adopted 2018 codes set no comparable sprinkler recommendation.
Fire Sprinkler Recommendation in Pocatello
Few RestrictionsPocatello City Code § 15.02.010
International Wildland-Urban Interface Code, 2018 edition, including: ... Amended as follows: ... - Section ... 602.1 General. An approved automatic sprinkler system is recommended in all occupancies in new buildings required to meet to meet the requirements for Class 1 ignition-resistant construction in Chapter 5. The installation of the automatic sprinkler systems shall be in accordance with ...
Building Permits
Pocatello requires a Building Department permit, secured by a licensed contractor, before any work regulated by the adopted International Building or Residential Codes begins, under City Code § 15.04.030. The city specifically declined to adopt the model codes' fence exemption, so fence installation needs a permit too, and § 15.04.040 doubles the fee or adds a misdemeanor citation for work that starts before the permit is issued.
Building Permits Required in Pocatello
Some RestrictionsPocatello City Code §§ 15.04.030, 15.04.040
15.04.030: PERMITS REQUIRED: ... A. Building, Residential, City Codes: Permits are required for construction activity regulated by the international building code, international residential building code, and this code. It shall be unlawful for any person to perform any work regulated thereby, or to have such work performed on his behalf, unless and until a permit for such work has been secured...
Electrical Permits
Pocatello adopted the 2023 National Electrical Code with Idaho IDAPA amendments at City Code § 15.02.010, and § 15.08.030 requires a Building Department permit for electrical work before it starts. A registered electrical contractor pulls the permit for most jobs, though owners wiring their own primary or secondary residence, in-house maintenance electricians, and certain utilities working on their own systems qualify for listed exceptions.
Electrical Permits Under Pocatello's NEC
Some RestrictionsPocatello City Code §§ 15.02.010, 15.08.030
National Electrical Code, 2023 edition, and appendix H, and additions and amendments to the National Electrical Code, 2023 edition, as identified in the current IDAPA Standards, 07.01.06. ... 15.08.030: ... PERMITS REQUIRED: ... A. Prior To Commencement Of Work: Permits are required for electrical work as defined in chapter 15.03 of this title and as set out in this chapter. It shall be unlawfu...
Plumbing Permits
Pocatello requires a permit from the Building Department before any plumbing work covered by the Idaho State Plumbing Code begins, secured by a licensed contractor. Owner-occupants building or working on their own single- or two-family home, and sewer or utility contractors working outside a building's foundation walls, are the only exceptions. Starting work before the permit issues doubles the fee and can bring a misdemeanor citation.
Pocatello Plumbing Permit Rules
Some RestrictionsPocatello City Code §§ 15.16.030, 15.16.040
15.16.030: PERMITS: A. Required: ... Permits are required for plumbing work as defined in chapter 15.03 of this title and as set out in this chapter. It shall be unlawful for any person to perform any work regulated thereby, or to have such work performed on his behalf, unless and until a permit for such work has been secured by a licensed contractor from the Building Department prior to the co...
Building Inspections
Pocatello requires contractors to obtain inspections in the proper sequence and secure a final inspection or certificate of occupancy under § 15.03.060, and it backs that duty with broad inspection access: § 15.04.070 lets the building official or another designated inspector enter any premises at any time construction work is underway, and § 15.08.050 gives the same right to the city electrical inspector for electrical work.
Building Inspection Access in Pocatello
Some RestrictionsPocatello City Code §§ 15.03.060, 15.04.070, 15.08.050
F. Obtain inspection services promptly and in the proper sequence when the same are required by this or any other ordinance of the city and maintain accessibility and visibility for the work until inspection and approval have been obtained. G. Obtain final inspections and certificates of occupancy or final inspection approval. ... 15.04.070: ... RIGHT TO INSPECT: ... The building official or ot...