Stormwater Management
In the City of Satellite Beach, every development must design its surface water runoff to match natural, pre-development rate, volume, quality and timing, treating at least the first inch of runoff on-site under Sec. 30-711. Sec. 30-712 sets a 50-year design life and requires plans certified by a licensed engineer.
Satellite Beach Stormwater Runoff Standards
Some RestrictionsSatellite Beach City Code § 30-711; § 30-712
Sec. 30-711. - Performance standards. All development and redevelopment shall be designed, constructed, and maintained so that the characteristics of surface water runoff shall approximate the rate, volume, quality, and timing of runoff that occurred under the site's natural unimproved state, except that at least the first inch of runoff shall be treated in an on-site retention system. ... Surf...
Erosion Control
In the City of Satellite Beach, every site plan submitted for development review must include a plan describing the type and location of erosion and sedimentation control measures, when they go into place during construction, and how they will be maintained, under Sec. 30-303(f)(2)g.1 of the city code.
Satellite Beach Construction Erosion Control Plan
Some RestrictionsSatellite Beach City Code § 30-303(f)(2)g.1
g.Surface water runoff management.1.A plan that describes the type and location of measures to control erosion and sedimentation, the stage of development at which they will be put into place or used, and maintenance provisions for the control measures.
Flood Zones
Satellite Beach's Floodplain Management Ordinance regulates all development in flood hazard areas, from subdivisions and fill to manufactured homes and pools. Flood hazard boundaries follow the 2014 Brevard County Flood Insurance Study and FIRM maps, and the Floodplain Administrator, the building official, issues permits before any qualifying work begins.
Satellite Beach Floodplain Development Rules
Some RestrictionsSatellite Beach City Code § 3-5, Floodplain Management Ordinance §§ 101.2, 102.3
101.2 Scope. ... The provisions of this ordinance shall apply to all development that is wholly within or partially within any flood hazard area, including but not limited to the subdivision of land; filling, grading, and other site improvements and utility installations; construction, alteration, remodeling, enlargement, improvement, replacement, repair, relocation or demolition of buildings, ...
Flood Elevation Requirements
Where a mapped Zone A has no published base flood elevation, Satellite Beach's Floodplain Administrator can set it at three feet above the highest adjacent grade. New or replaced critical facilities that cannot avoid a flood hazard area must have their lowest floor at least one foot above the 500-year floodplain elevation or the design flood elevation, whichever is higher.
Satellite Beach Base Flood Elevation Rules
Some RestrictionsSatellite Beach City Code § 3-5, Floodplain Management Ordinance §§ 105.2(3)(b), 202, 308.1(1)
Specify that the base flood elevation is three (3) feet above the highest adjacent grade at the location of the development, provided there is no evidence indicating flood depths have been or may be greater than three (3) feet. ... Base flood elevation. ... The elevation of the base flood, including wave height, relative to the National Geodetic Vertical Datum (NGVD), North American Vertical Da...
Looking for Brevard County county-wide rules?
County ordinances apply to unincorporated areas and may supplement Satellite Beach city rules.
Environmental Rules in Brevard County →