Cass County, MO Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)
Key Facts
- Permit required
- Special use permit (SUP)
- Maximum site size
- 1,000 acres unless BZA modifies
- Maximum lot coverage
- 60% of parcel
- Maximum height
- 40 feet from adjacent grade
- Enforcing department
- Zoning and Codes Department
Summary
A data center in unincorporated Cass County needs a special use permit and cannot exceed 1,000 acres, 60% lot coverage, or 40 feet in height. Battery storage, generators and substations built on the same site face their own siting rules under the same permit.
C. Required Approvals. A special use permit is required for a data center and/or battery energy storage system/battery storage facility. Any proposed expansion of such facilities will require approval of a new special use permit. ... 2. Size. ... In order to maintain the rural character and preserve agricultural land the data center site shall: a. Be limited to no more than one thousand (1,000) acres total, unless the BZA approves a modification from this standard b. ... Have a maximum of sixty percent (60%) coverage of the lot/parcel of land in which it is located on ... 7. Height. ... Data center and any appurtenant equipment shall not exceed forty (40) feet in height, measured from adjacent grade; including any roof-mounted mechanical equipment
Full Breakdown
662 governs data centers countywide in the unincorporated area. Subsection C requires a special use permit (SUP) for any data center or battery energy storage system, and any later expansion of the site area or accessory equipment area triggers a new SUP application rather than an administrative amendment. Subsection E sets numeric development standards meant to preserve the county's rural and agricultural character: the site is capped at 1,000 acres total unless the Board of Zoning Adjustment approves a modification based on site-specific characteristics tied to preserving rural character, natural features, or shared agricultural use, and lot coverage from all hard surfaces, structures and appurtenant equipment cannot exceed 60% of the parcel.
Structures and equipment are capped at 40 feet in height measured from adjacent grade, including roof-mounted mechanical equipment, though the BZA may approve additional height to accommodate slopes without grading or added screening if it will not harm nearby land uses. Location standards steer siting away from prime farmland disturbance, steep slopes of 15% or more, and environmentally sensitive lands such as floodways and wetlands, and push applicants toward brownfield sites and screening from off-site view. A primary structure is required before installing a standalone modular data center (SMDC), and every SMDC must be screened with landscaping, opaque fencing, or a decorative wall at least as tall as the SMDC; chain-link screening is not allowed.
Applications go to the Zoning and Codes Department, and the review considers visual impact, wildlife habitat, cultural and historical features, infrastructure impact, aviation/FAA concerns, and the applicant's decommissioning and bonding plan.
Violations & Fines
Operating a data center, battery storage system, generator, or substation in unincorporated Cass County without an approved special use permit, or expanding a permitted facility's site area or accessory equipment footprint without first obtaining a new SUP, is a code violation the Zoning and Codes Department enforces. Exceeding the 1,000-acre cap or 60% lot coverage standard without a BZA-approved modification, or building taller than 40 feet without an approved height modification, puts the facility out of compliance with its permit conditions.
Frequently Asked Questions
Can I build a data center in unincorporated Cass County by right?
How large can a data center site be in unincorporated Cass County?
How tall can data center structures be?
Sources & Official References
Other rules in Cass County
Compare Cass County to another location·View the Missouri data centers & crypto mining overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.