Frederick County, VA Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)
Key Facts
- Residential setback
- 200 ft from RA, RP, R4, R5, MH1
- Perimeter buffer
- Category C buffer required
- Buffer waiver
- Waived next to B3, TM, M1, M2
- Pre-approval studies
- Water, agriculture, parks, historic sites, forestland
- Governing section
- § 165-705.01.A(1), A(4)
Summary
In Frederick County outside Winchester, Stephens City and Middletown, a data center rezoning or CUP application must include site assessments on ground and surface water, agriculture, parks, historic sites and forestland, and § 165-705.01.A(4) requires a 200-foot structure setback from any adjoining RA, RP, R4, R5 or MH1 land plus a Category C buffer around the property.
A. All data centers must meet the following requirements: (1) Prior to the approval of a rezoning application or CUP, the following shall be provided: (a) A site assessment to examine the sound profile of the data center on residential units and schools located within 500 feet of the data center property boundary in accordance with Subsection A(5), below; ... (4) Setback and screening requirements. (a) Structures must be set back at least 200 feet from the common property line when adjoining land is zoned RA, RP, R4, R5, or MH1. Otherwise, the base zoning district dimensional standards shall apply in accordance with Article IV, Primary Zoning Districts. (b) A "Category C" zoning district buffer as described in Article VIII, Part 802, of this chapter, shall be provided around the perimeter of the property.
Full Breakdown
A, which conditions rezoning and conditional use permit approval on a package of upfront studies and fixed dimensional requirements rather than leaving siting to case-by-case discretion alone. Subsection A(1) requires, before approval, a site assessment examining the facility's sound profile on residential units and schools within 500 feet of the property boundary, plus a separate assessment of the proposed facility's effect on ground and surface water resources, agricultural resources, parks, registered historic sites, and forestland on the site or immediately contiguous land, along with details of any new or existing substations and the anticipated transmission voltage needed to serve the facility.
Subsection A(4) then sets the dimensional floor: structures must sit back at least 200 feet from the common property line wherever the adjoining land is zoned RA, RP, R4, R5 or MH1, with the base zoning district's dimensional standards under Article IV applying instead when the adjoining land carries a different zoning. A Category C zoning district buffer, defined in Article VIII, Part 802, must also wrap the property's perimeter, though that buffer is waived where the adjoining property is zoned B3, TM, M1 or M2.
Mechanical equipment siting is folded into the same standard: ground-mounted mechanical equipment is barred from the primary setback, and both ground-mounted and rooftop equipment must be screened from public roadways and adjoining properties, with generators enclosed in a manufacturer-approved enclosure or housed inside the primary structure.
Violations & Fines
A data center sited without the 200-foot residential setback, without the required Category C buffer, or without the upfront site assessments in § 165-705.01.A(1) is out of compliance with its rezoning or CUP conditions, enforceable by the Zoning Administrator under § 165-204.04; an uncorrected violation is a misdemeanor with a fine of $10 to $1,000 per offense, rising for repeated noncompliance.
Frequently Asked Questions
How far must a Frederick County data center be from homes?
What studies does a Frederick County data center need before rezoning approval?
Is a landscaped buffer required around a Frederick County data center?
Sources & Official References
Other rules in Frederick County
Compare Frederick County to another location·View the Virginia data centers & crypto mining overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.