Kyle, TX Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)
Key Facts
- Data centers permitted in
- Plum Creek PUD 'EMP' district only
- Min lot size
- 5,750 square feet
- Max height
- 75 feet
- Max FAR
- 1.5
- Setbacks
- None required (front/side/rear)
- Site plan review
- Architectural review committee letter required
Summary
In the City of Kyle, data centers are a permitted use only inside the Plum Creek Planned Unit Development's "EMP" employment district, not automatically citywide. Chapter 53A of the Kyle City Code lists "Data centers" among the district's by-right uses and applies standard EMP site development rules: a 5,750-square-foot minimum lot, a 75-foot height cap and a 1.5 floor area ratio.
(17) Data centers. (C) Site development regulations.A letter of approval from the architectural review committee shall be submitted with an application for a site plan. ... (3) The following regulations shall be applicable to the "EMP" employment district: (a) Minimum lot size: 5,750 square feet. (b) Minimum lot width: 50 feet. (c) Minimum lot depth: 100 feet. (d) Maximum height: No building or structure shall be erected, enlarged or structurally altered to exceed 75 feet. ... (g) Maximum floor area ratio: 1.5 FAR of the lot area.
Full Breakdown
Section 9 of the Plum Creek PUD zoning ordinance, Chapter 53A of the Kyle City Code adopted by Ordinance No. 311 on July 22, 1997 and amended by Ordinance 787 (2014) and Ordinance 832 (2015), establishes the "EMP" employment PUD district as an area for commercial businesses, services and industries compatible with adjacent residential neighborhoods. Subsection (B)(17) lists "Data centers" as the seventeenth permitted use in the district, alongside offices, warehouses, research and testing facilities, and light manufacturing and assembly uses. A data center sited in the EMP district must meet the district's site development regulations in subsection (C): a minimum lot size of 5,750 square feet, minimum lot width of 50 feet and lot depth of 100 feet, a maximum building height of 75 feet, and a maximum floor area ratio of 1.5.
Front, side and rear yard setbacks are not required in the EMP district. Development also needs a letter of approval from the architectural review committee submitted with the site plan application, paved sidewalks, driveways and parking areas, and screening of any loading and storage facilities. Because these standards sit inside the Plum Creek PUD exhibit, they apply only to EMP-zoned land within Plum Creek; a data center proposed elsewhere in Kyle would instead be evaluated against the city's standard Chapter 53 zoning use tables and any applicable overlay district.
Violations & Fines
Operating or building a data center in the EMP district without the required architectural review committee approval and site plan is a zoning violation. Kyle's general penalty, Code Section 1-14, punishes zoning violations by a fine of up to $2,000.00, with each day of continued noncompliance treated as a separate offense, enforced through the Planning and Community Development Department's code compliance process.
Frequently Asked Questions
Are data centers allowed anywhere in Kyle?
How tall can a data center be in Plum Creek's EMP district?
Does a data center need site plan approval in Kyle?
Sources & Official References
Other rules in Kyle
Texas rules heatmap·Compare Kyle to another location·View the Texas data centers & crypto mining overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.