Spotsylvania County, VA Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Use classification
Data Center (special use, most districts)
Approval body
Board of Supervisors special use permit
Water restriction
No permanent potable water cooling
Water appeal window
30 days to Board of Supervisors
Governing sections
§§ 23-2.1.4, 23-6.15.3, 22-47

Summary

Spotsylvania County treats data centers as a distinct zoning use requiring board-of-supervisors special use approval in most commercial and office districts, including Offices 1 (O-1). The county also bars data centers from permanent use of public drinking water for cooling, limiting them to backup or temporary use of the county water system.

These county ordinances apply to unincorporated areas of Spotsylvania County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Sec. 23-6.15.3. - Special uses. The following uses may be established as special uses in the offices 1 (O-1) district, subject to approval by the board of supervisors in accordance with the procedures established in article 4, division 5 of this chapter: (1)Business service and supply establishment;(2)Convenience store, inconsistent with the use allowed by-right herein;(3)Data Center;

Full Breakdown

§ 23-2.1.4 defines a Data Center as "a facility used primarily for the storage, management, processing, and transmission of digital data," including its computer and network equipment, air handlers, power generators, water cooling and storage facilities, and utility substations. The zoning ordinance repeatedly places Data Center on the special-use list rather than the by-right list: § 23-6.15.3 lists it as a special use in the Offices 1 (O-1) district, and the same special-use treatment recurs in Offices 2, the county's general business and commercial districts, and several industrial classifications, meaning a data center needs board of supervisors approval under the § 23-4.5 special-use procedure in nearly every zoning category it appears in. That process requires a generalized development plan, planning commission review and a public hearing, and board findings under the § 23-4.5.7(a) general standards, covering traffic, environmental impact, and compatibility with the neighborhood.

Beyond zoning, § 22-47 of the water and sewer chapter separately restricts data center water use: "Any data center or similar user of Spotsylvania County water shall not use public potable source water for permanent cooling water purposes." Only temporary, supplemental, or emergency cooling use of the public water system may be approved by the director of utilities, who may limit that use by time, volume, or flow to protect the water system, and who may terminate approval at any time it is no longer consistent with sound system management. An applicant aggrieved by the director's decision may appeal to the board of supervisors within thirty days.

Because Spotsylvania County is a separate jurisdiction from the independent City of Fredericksburg next door, a proposed data center must be sited on county-zoned parcels and reviewed under the county's own code; a Fredericksburg approval has no bearing on a county application.

Violations & Fines

Beginning construction or operating a data center without the required special use approval and site plan under § 23-4.5.2 is a zoning violation subject to the zoning administrator's enforcement under § 23-9.1.1, escalating to a misdemeanor fine of $10 to $1,000 per § 23-9.1.2. Using public potable water for permanent cooling without authorization violates § 22-47 and can result in the director of utilities terminating water service for that use.

Frequently Asked Questions

Is a data center allowed by right anywhere in Spotsylvania County?
Not typically. The zoning ordinance lists Data Center as a special use, meaning it needs board of supervisors approval, in the Offices 1 and Offices 2 districts and in the county's general business and commercial districts under sections such as § 23-6.15.3. That approval requires a public hearing and generalized development plan, not just a building permit.
Can a data center in Spotsylvania County use county drinking water to cool its servers?
No, not on a permanent basis. Section 22-47 specifically bars data centers from using public potable source water for permanent cooling. The director of utilities may approve temporary, supplemental, or emergency use only, and can limit or terminate that use to protect the county's water system.
What must a data center applicant submit for special use approval?
Under § 23-4.5.3, applicants must file a generalized development plan showing building height, setbacks, parking, landscaping, stormwater facilities, and traffic generation, plus a title block with the tax map reference. The planning commission then holds a public hearing before recommending approval, denial, or modification to the board of supervisors.

Sources & Official References

Other rules in Spotsylvania County

All Spotsylvania County rules

Compare Spotsylvania County to another location·View the Virginia data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Spotsylvania County, VA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.